Working 5 hours a day. A can' complete a...

Working 5 hours a day. A can' complete a work in 8 days and working 6 hours a day, B can complete the same work in 10 days. Working 8 hours a day, they can jointly complete the work in

A

3 days

B

4 days

C

4.5 days

D

5.4 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the total amount of work done by A and B individually, and then find out how long they take to complete the work together when working 8 hours a day. ### Step 1: Calculate the total work done by A A works for 5 hours a day and can complete the work in 8 days. - Total work done by A = hours worked per day × number of days - Total work done by A = 5 hours/day × 8 days = 40 hours ### Step 2: Calculate the total work done by B B works for 6 hours a day and can complete the work in 10 days. - Total work done by B = hours worked per day × number of days - Total work done by B = 6 hours/day × 10 days = 60 hours ### Step 3: Calculate the work rate of A and B The work rate is the fraction of work completed in one hour. - Work rate of A = 1/Total work done by A = 1/40 - Work rate of B = 1/Total work done by B = 1/60 ### Step 4: Calculate the combined work rate of A and B To find the combined work rate when A and B work together, we add their individual work rates: - Combined work rate = Work rate of A + Work rate of B - Combined work rate = 1/40 + 1/60 To add these fractions, we need a common denominator. The least common multiple (LCM) of 40 and 60 is 120. - 1/40 = 3/120 - 1/60 = 2/120 - Combined work rate = 3/120 + 2/120 = 5/120 = 1/24 ### Step 5: Calculate the time taken to complete the work together If A and B can complete 1/24 of the work in one hour, then the total time taken to complete the entire work is the reciprocal of their combined work rate: - Time taken = 1 / (1/24) = 24 hours ### Step 6: Calculate the time taken when working 8 hours a day Now, we need to determine how many days it will take them to complete the work if they work 8 hours a day: - Total hours needed = 24 hours - Days needed = Total hours needed / hours worked per day - Days needed = 24 hours / 8 hours/day = 3 days ### Final Answer Therefore, working together for 8 hours a day, A and B can complete the work in **3 days**.
Promotional Banner

Similar Questions

Explore conceptually related problems

Working 2 hours in a day, P can complete a work in 10 days and working 5 hours in a day, Q can complete the same work in 6 days. Working 3 hours in a day, in how many days both P and Q together can complete the same work?

10 men working 6 hours a day can complete a work in 18 days. How many hours a day must 15 men work to complete the same work in 12 days.

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how man days can they complete the work ?

P can complete a work in 12 days working 8 hours a day. Q can complete the same work in 8 days working 10 hours a day. If both P and Q work together, working 8 hours a day, in how many days can they complete the work ? 5 5/(11) b. 5 6/(11) c. 6 6/(11) d. 6 6/(11)