40 men can complete a work in 40 days. T...

40 men can complete a work in 40 days. They started the work together. But at the end of each 10th day, 5 men left the job. The work would have been completed in

A

`56"" (2)/(3)` days

B

`53 "" (1)/(3)` days

C

`52` days

D

50 days

Text Solution

Verified by Experts

The correct Answer is:
A