A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

A

10 days

B

12 days

C

15 days

D

16 days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Similar Questions

Explore conceptually related problems

Working together A, B and C can complete a piece of work in 24 days. After working together for 4 days. C left the work. A and B completed the remaining work in 30 days. The number of days taken by C alone to complete the same work is:

A can do a piece of work in 20 days while B can do it in 30 days. Both of them start the work together and work for some time, then B leaves. If A completes the remaining work in 10 days, then find the number of days for which they worked together.