A contractor undertook to finish a certa...

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done `2/3` of the work.
How many men can be discharged now so that the work may finish in time?

A

48

B

56

C

40

D

50

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Similar Questions

Explore conceptually related problems

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. The number of additional men that should be appointed so that the whole work will be finished in time is: (A) 50 (B) 75 (C) 100 (D) 150

90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?