A man can do a piece of work in 5 days, but with the help of his son, he can do it in 3 days. In what time can the son do it alone ?

A

7 days

B

8 days

C

`7 (1)/(2)` days

D

`6 (1)/(2)` days

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Similar Questions

Explore conceptually related problems

A man can do a piece of work in 5 days, but with the help of his son he can do the same work in 3 days. In what time can the son do it alone?

A man can do a piece of work in 5 days . With the help of his friend , he can do the same work in 3 days . In how many days can his friend complete the work?

A man can do a piece of work in 5 days. He and his son working together can finish it in 3 days. In how many days can the son do it alone?

A and B can do a piece of work in 72 days, B and C can do it in 120 days while A and C can do it in 90 days. In what time can A alone do it?

A and B can do a piece of wok in 72 days, B and C can do it in 120 days, A and C can do it in 90 days. In what time can A alone do it ?

Total wages for a work is Rs.1280.A alone can do a piece of work in 8 days, while B alone can do it in 12 days. If A and B work on alternate days, then find the share of A.