Home
Class 14
MATHS
A can finish a work in 24 days, B in 9 d...

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but they are forced to leave after 3 days. The remaining work was done by A in

A

10 days

B

`10 (1)/(2) days`

C

`5 days`

D

` 6 days`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these instructions: ### Step 1: Determine the total work We need to find the least common multiple (LCM) of the days taken by A, B, and C to finish the work. - A can finish the work in 24 days. - B can finish the work in 9 days. - C can finish the work in 12 days. **Calculation of LCM:** - The LCM of 24, 9, and 12 is 72. **Total work = 72 units.** ### Step 2: Calculate the efficiency of A, B, and C Now we will calculate how much work each person can do in one day (their efficiency). - **Efficiency of A:** \[ \text{Efficiency of A} = \frac{72 \text{ units}}{24 \text{ days}} = 3 \text{ units/day} \] - **Efficiency of B:** \[ \text{Efficiency of B} = \frac{72 \text{ units}}{9 \text{ days}} = 8 \text{ units/day} \] - **Efficiency of C:** \[ \text{Efficiency of C} = \frac{72 \text{ units}}{12 \text{ days}} = 6 \text{ units/day} \] ### Step 3: Calculate the work done by B and C in 3 days B and C work together for 3 days. We need to find the total work done by both in that time. - **Total efficiency of B and C:** \[ \text{Total efficiency} = \text{Efficiency of B} + \text{Efficiency of C} = 8 + 6 = 14 \text{ units/day} \] - **Work done in 3 days:** \[ \text{Work done} = \text{Total efficiency} \times \text{Time} = 14 \times 3 = 42 \text{ units} \] ### Step 4: Calculate the remaining work Now we will find out how much work is left after B and C have worked for 3 days. - **Remaining work:** \[ \text{Remaining work} = \text{Total work} - \text{Work done by B and C} = 72 - 42 = 30 \text{ units} \] ### Step 5: Calculate the time taken by A to finish the remaining work Now we need to determine how long it will take A to complete the remaining 30 units of work. - **Time taken by A:** \[ \text{Time} = \frac{\text{Remaining work}}{\text{Efficiency of A}} = \frac{30 \text{ units}}{3 \text{ units/day}} = 10 \text{ days} \] ### Final Answer The remaining work was done by A in **10 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

A can finish a work in 24 days, B in 9 days and C in 12 days. B and C start the work but are forced to leave after 3 days. The remaining work was done by A in:

A can complete a piece of work in 18 days, B in 20 days and C in 30 days. B and C together start the work and are forced to leave after 2 days. The time taken by A alone to complete the remaining work is

A and B can finish a work in 10 days while B and C can do it in 18 days. A started the work, worked for 5 days, then B worked for 10 days and the remaining work was finished by C in 15 days. In how many days could C alone have finished the whole work ? A)30 days B)15 days C)45 days D)24 days