A alone can complete a piece of work of ...

A alone can complete a piece of work of Rs. 300 in 6 days; but by engaging an assistant,the work is completed in 4 days. Find the share to be received by the assistant.

Promotional Banner

Similar Questions

Explore conceptually related problems

Raghu agrees to complete a work for 8.400 in 16 days. But by engaging an assistant, the work is complete in 12 days. Find the share of money remuneration to be received by the assitant.

A alone can complete a work ₹ 6,500 in 15 days. With the help of B the work is completed in 12 days. the share of B is

A and B undertake to complete a piece of work for Rupees 1200. A can do it in 8 days, B can do it in 12 days and with the help of C they complete the work in 4 days. Find the share of C ?

A alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?

a can complete a piece of work in 15 days. B can complete it in 10 days. With the help C, they can complete it in 4 days. They all worked togther and earned a total of s. 750. Find C's share.

1 man and 1 woman together can complete a piece of work in 8 days. A man alone can complete the work in 10 days. In how many days, can one woman alone complete the work?