Home
Class 14
MATHS
X and Y can do a piece of work in 30 day...

X and Y can do a piece of work in 30 days. They work together for 6 days and thenX quits and Y finishes the work in 32 days . In how many days can Y do the piece of work alone ?

A

30 days

B

32 days

C

34 days

D

40 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we need to determine how many days Y can complete the work alone. Let's break down the solution step by step. ### Step 1: Determine the work done by X and Y together Given that X and Y can complete the work together in 30 days, we can express their combined work rate as: \[ \text{Work done in 1 day by X and Y} = \frac{1}{30} \text{ of the total work (W)} \] Let the work done by X in one day be \( x \) and the work done by Y in one day be \( y \). Therefore, we have: \[ x + y = \frac{W}{30} \tag{1} \] ### Step 2: Calculate the work done in 6 days When X and Y work together for 6 days, the amount of work they complete is: \[ \text{Work done in 6 days} = 6(x + y) = 6 \cdot \frac{W}{30} = \frac{W}{5} \tag{2} \] ### Step 3: Determine the remaining work after 6 days After working together for 6 days, the remaining work is: \[ \text{Remaining work} = W - \frac{W}{5} = \frac{4W}{5} \tag{3} \] ### Step 4: Calculate the work done by Y alone After 6 days, X quits, and Y completes the remaining work in 32 days. The work done by Y in 32 days is: \[ \text{Work done by Y in 32 days} = 32y \] Since this work equals the remaining work, we have: \[ 32y = \frac{4W}{5} \tag{4} \] ### Step 5: Relate Y's work rate to the total work From equation (4), we can express \( y \) in terms of \( W \): \[ y = \frac{4W}{5 \cdot 32} = \frac{W}{40} \tag{5} \] ### Step 6: Substitute \( y \) back into equation (1) Now we substitute \( y \) from equation (5) into equation (1): \[ x + \frac{W}{40} = \frac{W}{30} \] To solve for \( x \), we need a common denominator. The least common multiple of 30 and 40 is 120. Thus, we rewrite the equation: \[ x + \frac{3W}{120} = \frac{4W}{120} \] Subtracting \( \frac{3W}{120} \) from both sides gives: \[ x = \frac{4W}{120} - \frac{3W}{120} = \frac{W}{120} \tag{6} \] ### Step 7: Find the total work in terms of Y's work rate Now we know both \( x \) and \( y \): - \( x = \frac{W}{120} \) - \( y = \frac{W}{40} \) ### Step 8: Determine how many days Y takes to complete the work alone Let \( d \) be the number of days Y takes to complete the work alone. Then: \[ d \cdot y = W \] Substituting \( y \) from equation (5): \[ d \cdot \frac{W}{40} = W \] Dividing both sides by \( W \) (assuming \( W \neq 0 \)): \[ \frac{d}{40} = 1 \implies d = 40 \] ### Final Answer Y can complete the piece of work alone in **40 days**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

A can do a piece of work in 5 days, B can do it in 10 days. With the help of C, they finish the work in 2 days. In how many days C alone can do the whole work?

A can do a piece of work in 10 days, B can do it in 15 days working together they can finish the work in :

A can do a piece of work in 12 days and B in 15 days. With help of C, they finish the work in 4 days. In how many days C alone can do the same work?