Home
Class 14
MATHS
A can complete a work in 20 days and B c...

A can complete a work in 20 days and B can complete the same work in 25 days . If both of them work together, in 3 days what per cant of the total work will be completed ?

A

9

B

12

C

25

D

27

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work rates of A and B, then calculate how much work they complete together in 3 days, and finally convert that into a percentage of the total work. ### Step 1: Determine the work rates of A and B - A can complete the work in 20 days. Therefore, A's work rate is: \[ \text{Work rate of A} = \frac{1}{20} \text{ work per day} \] - B can complete the work in 25 days. Therefore, B's work rate is: \[ \text{Work rate of B} = \frac{1}{25} \text{ work per day} \] ### Step 2: Calculate the combined work rate of A and B - When A and B work together, their combined work rate is: \[ \text{Combined work rate} = \text{Work rate of A} + \text{Work rate of B} = \frac{1}{20} + \frac{1}{25} \] - To add these fractions, we need a common denominator. The least common multiple of 20 and 25 is 100. \[ \frac{1}{20} = \frac{5}{100}, \quad \frac{1}{25} = \frac{4}{100} \] \[ \text{Combined work rate} = \frac{5}{100} + \frac{4}{100} = \frac{9}{100} \text{ work per day} \] ### Step 3: Calculate the total work done in 3 days - In 3 days, the amount of work completed by A and B together is: \[ \text{Work completed in 3 days} = \text{Combined work rate} \times 3 = \frac{9}{100} \times 3 = \frac{27}{100} \] ### Step 4: Convert the work done into a percentage of the total work - To find the percentage of the total work completed, we multiply the fraction of work completed by 100: \[ \text{Percentage of work completed} = \frac{27}{100} \times 100 = 27\% \] ### Final Answer Thus, the percentage of the total work completed by A and B together in 3 days is **27%**. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

Manish can complete a work in 21 days and Karan can complete the same work in 28 days. If both together work for 7 days, then what fraction of total work is left?

A can complete a work in 20 days & B can complete the same work in 25 days. If they start the work together but After 5 days A left the work . In how many days the total work would be finished ?

A alone can complete a work in 10 days and B alone can complete the same work in 20 days. In how many days both 4 and B together can complete half of the total work?

A can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.

A can complete a piece of work in 18 days and B can complete the same work in half time taken by A. Then, working together, what part of the same work they can complete in a day?