P and Q can individually complete a piec...

`P` and `Q` can individually complete a piece of work in `15` and `25` days,respectively.In how many days can `P` and `Q` complete the work if they work on alternate days: (A) Starting with `P` and (B) Starting with `Q`

Promotional Banner

Similar Questions

Explore conceptually related problems

P and Q can individually complete a piece of work in 15 and 25 days respectively.In how many days can P and Q complete the work if they work in alternative days ? Starting with P Starting with Q?

P and Q can individually complete a piece of work in 15 and 25 days respectively.In how many days can P and Q complete the work if they work in alternative days ? Starting with P Starting with Q?

Rishikesh and Mukesh can individually complete a piece of work in 18 days and 24 days respectively. On which day will the work be completed, If they work on alternate days starting with Rishikesh ?

Rishikesh and Mukesh can individually complete a piece of work in 18 days and 24 days respectively. On which day will the work be completed, If they work on alternate days starting with Rishikesh ?

P can complete a work in 72 days. Q is 33.33% more efficient than P. In how many days both complete the work if they work on alternate days starting with P?