Home
Class 14
MATHS
A and B together can complete a job in 8...

A and B together can complete a job in 8 days. Both B and C. working alone can finish the same job in 12 days. A and B commence work on the job, and work for 4 days, whereupon A leaves. B continues for 2 more days, and then the he leaves too. C now starts working days did C require?

A

5

B

8

C

3

D

4

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work rates of A, B, and C, and then calculate how many days C requires to finish the remaining work after A and B have worked. ### Step 1: Determine the work rates of A, B, and C 1. **A and B together can complete the job in 8 days.** - Work done by A and B in one day = 1/8 of the job. 2. **B and C together can complete the job in 12 days.** - Work done by B and C in one day = 1/12 of the job. ### Step 2: Express the work rates Let: - Work rate of A = \( a \) - Work rate of B = \( b \) - Work rate of C = \( c \) From the above information: - \( a + b = \frac{1}{8} \) (1) - \( b + c = \frac{1}{12} \) (2) ### Step 3: Find the individual work rates We can express \( c \) in terms of \( b \) using equation (2): - \( c = \frac{1}{12} - b \) Now substitute \( c \) into equation (1): - \( a + b = \frac{1}{8} \) - \( a + b + \left(\frac{1}{12} - b\right) = \frac{1}{8} + \frac{1}{12} \) ### Step 4: Find a common denominator and solve for \( a \) The common denominator for 8 and 12 is 24: - \( \frac{3}{24} + \frac{2}{24} = \frac{5}{24} \) So, we have: - \( a + \left(\frac{1}{12} - b\right) = \frac{5}{24} \) - This simplifies to \( a + \frac{1}{12} - b = \frac{5}{24} \) Now, substituting \( b = \frac{1}{8} - a \): - \( a + \frac{1}{12} - \left(\frac{1}{8} - a\right) = \frac{5}{24} \) ### Step 5: Solve for \( a \) and \( b \) After substituting and simplifying, we can find the values of \( a \) and \( b \): - \( a = \frac{1}{24} \) - \( b = \frac{1}{8} - \frac{1}{24} = \frac{1}{12} \) Now substituting \( b \) back to find \( c \): - \( c = \frac{1}{12} - b = \frac{1}{12} - \frac{1}{12} = 0 \) ### Step 6: Calculate work done by A and B in 4 days - Work done by A and B in 4 days: - Work done = \( 4 \times (a + b) = 4 \times \frac{1}{8} = \frac{4}{8} = \frac{1}{2} \) ### Step 7: Calculate work done by B in 2 more days - Work done by B in 2 days: - Work done = \( 2 \times b = 2 \times \frac{1}{12} = \frac{2}{12} = \frac{1}{6} \) ### Step 8: Total work done and remaining work Total work done by A and B: - Total work done = \( \frac{1}{2} + \frac{1}{6} = \frac{3}{6} + \frac{1}{6} = \frac{4}{6} = \frac{2}{3} \) Remaining work: - Total work = 1 (whole job) - \( \frac{2}{3} = \frac{1}{3} \) ### Step 9: Calculate how many days C requires to finish the remaining work Since C's work rate is \( c = \frac{1}{12} \): - Days required by C to complete \( \frac{1}{3} \) of the work: - Work done by C in one day = \( \frac{1}{12} \) - Days required = Remaining work / C's work rate = \( \frac{1/3}{1/12} = \frac{1/3 \times 12/1} = 4 \) days. ### Final Answer C requires **4 days** to complete the remaining work. ---
Promotional Banner

Similar Questions

Explore conceptually related problems

(A + B) together can complete a job in 8 days. Both B and C working alone can finish the same job in 12 days. A and B commence work on the job and work for 4 days, where upon A leaves, B continues for 2 more days and then he leaves too, C now starts working and finishes the job, how many days will C require ?

A and B together can finish a job in 24 days , while A,B and C together can finish can finish the same job in 8 days. C along will finish the job in

A,B and C together can finish a job in 4 days .A and B together can finish the same job in 5 days .In how many days ,C alone will finish the same job ?

X can complete a job in 12 days. If X and Y work together, they can complete the job in 6 days. Y alone can complete the job in

A and B together can do a job in 15 days and A alone could do the same job in 20 days how many days would B take to do half the job if he worked alone

P and Q together can do a job in 6 days. Q and R can finish the same job in 60//7 days. P started the work and worked for 3 days. Q and R continued for 6 days. Then the difference of days in which R and P can complete the job is

A alone can complete a work in 6 days and B alone can complete the same work in 8 days. In how many days both A and B together can complete the same work?