150 workers were engaged to finish a job...

150 workers were engaged to finish a job in a certain number of days. 4 workers dropped out on second day, 4 more workers dropped out on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed.

Text Solution

Verified by Experts

The correct Answer is:
25 days
Promotional Banner

Similar Questions

Explore conceptually related problems

150 workers were engaged to finish a piece of work in a certain number of days. Four workers dropped from the work on the second day. Four workers dropped on third day and so on. It took 8 more days to finish the work. Find the number of days in which the work was completed. [Let the no.of days to finish the work is 'x' then 150 x = (x+8)/2 [2 xx 150 + (x+8-1)(-4)]

4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish in 7 days. Find the time taken by 1 man alone and 1 boy alone to finish the piece of work.

A cottage industry produces a certain number of pottery articles in a day . It was observed on a particular day that the cost of production of each article (in rupees ) was 3 more than twice the number of articles produced on that day. If the total cost of production on that day was 90 , find the number of articles profit and the cost of each article.

Formulate the following problems as a pair of equations. 2 women and 5 men can together finish an embroidery work in 4 days, while 3 women and 6 men finish it in 3 days. Find the time taken by 1 woman alone to finish the work and also that taken by 1 man alone.

Shweta takes 6 days less , than the Ankitha to complete the work. The same work is completed together in 4 days. How many days required to complete the work by Ankitha alone?

A contract on construction job specifies a penalty for delay of completionbeyond a certain data as follows: Rs 200 for the first day , Rs250 for the second day, Rs 300 for the third day , etc., the penalty for each succeeding day being Rs50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 30 days ?

A' takes 6 days less than 'B' to complete a piece of work. If both work together they can complete the same work in 4 days. In how many days will 'B' alone complete the work?

A contract on construction job specific a penalty for delay of completion beyond a certain date as follows : Rs. 200 for the first day, Rs.250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?

Solve the problems. A cottage industry produces a certain number of toys in a day. The cost of production of each toy (in rupees) was found to be 55 minus the number of toys produced in a day . On a particular day, the total cost of production was 750 We would like to find out the number of toys produced on that day.