A contractor estimates that 3 persons could rewire Jasminder’s house in 4 days. If, he uses 4 persons instead of three, how long should they take to complete the job?

Text Solution

Verified by Experts

let no of ays taken =`x` days
`3*4 = 4*x`
`x = (3*4)/4`
`= 3`days
answer
Promotional Banner

Topper's Solved these Questions

  • DIRECT AND INVERSE PROPORTIONS

    NCERT|Exercise SOLVED EXAMPLES|8 Videos
  • DIRECT AND INVERSE PROPORTIONS

    NCERT|Exercise SOLVED EXAMPLES|8 Videos
  • DATA HANDLING

    NCERT|Exercise EXERCISE 5.1|5 Videos
  • EXPONENTS AND POWERS

    NCERT|Exercise SOLVED EXAMPLES|9 Videos

Similar Questions

Explore conceptually related problems

12 worker take 4 hours to complete a job.How long would it take 15 workers to complete the job?

If 3 persons can do a piece of work in 4 days, then 4 persons can do it in …… days.

10 people could complete a task in 8 days. After 4 days, 2 of the workers left. How many days from then did it take to complete the task?

A contractor undertakes to complete a work in 20 days. He employs 30 labourers on this job. How many more labourers would he employ to complete the work in 15 days?

Two persons could fit new windows in a house in 3 days.(i) One of the persons fell ill before the work started.How long would the job take now? (ii) How many persons would be needed to fit the windows in one day?

48 people could complete a task in 17 days .After 6 days , 4 of the workers left . How many days from then will it take to complete the task ?

A team of workers was employed by a contractor who undertook to finish 360 pieces of an article in a certain number of days. Making four more pieces per day than was planned, they could complete the job a day ahead of schedule. How many days did they take to complete the job? 8 d a y s b. 12 d a y s c. 9 d a y s d. 10 d a y s