A constrator employed 210 men to build a...

A constrator employed 210 men to build a house in 60 days. After 12 days.he was joined by 70 more men. In how many days will the remaining work be finished?
Hint. 210 men can complete the remaning work in 48 days.Find in how many days 280 men can do it.

Promotional Banner

Similar Questions

Explore conceptually related problems

If 15 men can complete a piece of work in 30 days, in how many days will 18 men complete it ?

36 men can do a piece of work in 12 days. In how many days 9 men can do the same work?

If 10 men can complete a work in 12 days . In how many days can 18 men complete the same work ?

7 men can complete a work in 52 days. In how many days will 13 men finish the same work.

If 52 men can do a piece of work in 35 days in how many days 28 men will do it?

If 52 men can do a piece of work in 35 days in how many days 28 men will do it ?

12 men can complete one third of the work in 8 days.In how many days can 16 men complete that work?

8 men can do a piece of work in 15 days. Find in how many days will 10 men finish the same work.