2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy to do it?

Promotional Banner

Similar Questions

Explore conceptually related problems

2 men and 7 boys can do a piece of work in 4 days. The same work is done in 3 days by 4 men and 4 boys. How long would it take one man and one boy alone to do it ?

2 men and 7 boys can do a piece of work in 4 days. It is done by 4 men and 4 boys in 3 days. How long would it take for one man or one boy to do it ?

One man and 2 boys can do a piece of work in 12 days.The same work can also be done by 3 men and 1 boy in 6days.How long it would take for one man alone to complete the work?

2 men and 5 boys can do a piece of work in 4 days, while 4 men and 4 boys can do it in 3 days. How long would it take one man alone to do it and how many days would it take one boy alone to do it ?

3 men and 4 boys can do a piece of work in 14 days, while 4 men and 6 boys can do it in 10 days. How long would it take 1 boy to finish the work?

6 men and 8 boys can do a piece of work in 7 days, while 8 men and 12 boys do the same work in 5 days. How long would it take one boy to finish the same work?

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?