Home
Class 14
MATHS
A contractor undertakes to make a road i...

A contractor undertakes to make a road in 40 days and employs 25 men. After 24 days, he finds that only onethird of the road is made. How many extra men should he employ so that he is able to complete the work 4 days earlier?

A

100

B

60

C

75

D

None of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow a structured approach: ### Step 1: Understand the Problem The contractor has 40 days to complete a road with 25 men. After 24 days, only one-third of the road is completed. He needs to finish the remaining two-thirds of the road in 36 days (4 days earlier than planned). **Hint:** Break down the total work into fractions to understand how much is left and how much time is available. ### Step 2: Calculate the Work Done In 24 days, 25 men completed one-third of the road. Let the total work be represented as W. - Work done in 24 days = \( \frac{1}{3}W \) **Hint:** Use the formula for work done: Work = Number of men × Number of days. ### Step 3: Calculate the Remaining Work The remaining work is: - Remaining work = Total work - Work done = \( W - \frac{1}{3}W = \frac{2}{3}W \) **Hint:** Always check how much work is left after a certain period. ### Step 4: Determine the Time Left The contractor now has 36 days to complete the remaining work. **Hint:** Keep track of the time constraints to ensure the work can be completed on schedule. ### Step 5: Set Up the Equation Let \( x \) be the number of extra men to be employed. The total number of men after hiring extra men will be \( 25 + x \). The equation using the work formula is: \[ (25 + x) \times 36 = \frac{2}{3}W \] From the first part, we know: \[ 25 \times 24 = \frac{1}{3}W \implies W = 25 \times 24 \times 3 = 1800 \] Now substitute \( W \) into the equation: \[ (25 + x) \times 36 = \frac{2}{3} \times 1800 \] **Hint:** Substitute known values to simplify the equation. ### Step 6: Simplify the Equation Calculate \( \frac{2}{3} \times 1800 \): \[ \frac{2}{3} \times 1800 = 1200 \] So the equation becomes: \[ (25 + x) \times 36 = 1200 \] **Hint:** Always simplify your calculations to make the problem easier to solve. ### Step 7: Solve for \( x \) Now divide both sides by 36: \[ 25 + x = \frac{1200}{36} = 33.33 \] Now, subtract 25 from both sides: \[ x = 33.33 - 25 = 8.33 \] Since \( x \) must be a whole number, we round up to the nearest whole number: \[ x = 9 \] **Hint:** When dealing with people, always round up to ensure you have enough workers. ### Step 8: Conclusion The contractor needs to hire 9 extra men to complete the work in 36 days. **Final Answer:** The contractor should employ **9 extra men**.
Promotional Banner

Similar Questions

Explore conceptually related problems

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

A contractor undertakes to built a walls in 50 days. He employs 50 peoples for the same. However after 25 days he finds that only 40% of the work is complete. How many more man need to be employed to complete the work in time?

A man undertakes to do a certain work in 150 days. He employs 200 men. He finds that only a quarter of the work is done in 50 days. How many additional men should he employ so that the whole work is finished in time ?

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that he had already done 2/3 of the work. How many men can be discharged now, so that the work may finish in time ?

A contractor undertook to finish a certain work in 124 days and employed 120 men. After 64 days, he found that they had already done 2/3 of the work. How many men can be discharged now so that the work inay finish in time?