A can do a piece of work in 7 days of 9 ...

A can do a piece of work in 7 days of 9 hours each and B can do it in 6 days of 7 hours each. How long will they take to do it, working a together `8 2/5`a day?

Promotional Banner

Similar Questions

Explore conceptually related problems

Amit can do a piece of work in 4 days and Sumit can do it in 6 days How long will they take, if both Amit and Sumit work together ?

Amit can do a piece of work in 4 days and Sumit can do it in 6 days How long will they take, if both Amit and Sumit work together ?

Raj can do a piece of work in 20 days and Rohan can do it in 12 days. How long will they take, if both work together?

A can do a piece of work in 10 days and B in 15 days. How long will they take to finish it working together ?

A can do one-third of a piece of work in 4 days and B can do one-fourth of the work in 6 days. How long will they take to complete the work, working together ?

A can do one-third of a piece of work in 4 days and B can do one-fourth of the work in 6 days. How long will they take to complete the work, working together ?