Visitors to a show were charged Rs. 12 e...

Visitors to a show were charged Rs. 12 each on the first day, Rs. 9.0 on the second Rs. 4 on the third day and the total attendance on three days were in the ratio 3:6:11 respectively. Find the average charge per person for the whole show.

Promotional Banner

Similar Questions

Explore conceptually related problems

Visitors to a show were charged Rs 15 each on the first day, Rs 7.50 each on the second day and Rs 2.50 each on the third day. The attendance on the three days was in the ratio 2 : 5 : 13. The average charge per person for the whole show was (a) Rs 5 (b) Rs 6.33 (c) Rs 7.50 (d) 9

A boy spends Rs. 10 on first day, Rs. 20 on second day, Rs. 40 on third day and so on. Find how much, in all, will he spend in 12 days ?

Ram gives his son Rs. 100 on one day, Rs. 50 on the second day, Rs. 25 on third day and so on. What will be total amount given by Ram to his son starting from the first day, if he lives forever?

A contract on construction job specific a penalty for delay of completion beyond a certain date as follows : Rs. 200 for the first day, Rs.250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

A can do a piece of work in 90 days, B in 40 days and C in 12 days. They work for a day each in turn i.e., first day A does it alone, B does it the second day and C the third day. After that A does it for another day, and so on. After finishing the work they get Rs. 240.If the wages are divided in proportion to the work done by them, find what each will get. a. A Rs. 24, B Rs. 54 and C Rs. 162 b. A Rs. 22, B Rs. 50 and C Rs. 132 c. A Rs. 26, B Rs. 52 and C Rs. 142 d. A Rs. 20, B Rs. 44 and C Rs. 182