X and Y can do a piece of work in 20 day...

X and Y can do a piece of work in 20 days and 30 days respectively. The time they take to complete the work by working together is ……………

Promotional Banner

Similar Questions

Explore conceptually related problems

If A,B and C can respectively complete a piece of work in 20,24 and 36 days respectively .how many days will they take to complete the work, if they work together?

Gauthan and Karthik can do a piece of work in 10 days and 20 days respectively. With the help of Nilesh, they can complete the whole work in 5 days. In how many days can Nilesh alone complete the work ?

Gauthan and Karthik can do a piece of work in 10 days and 20 days respectively. With the help of Nilesh, they can complete the whole work in 5 days. In how many days can Nilesh alone complete the work ?

A, B and C can do a piece of work in10 days, 12 days and 15 days respectively. How long will they take to finish it if they work together?

A and B can do a piece of work in 20 days and 30 days respectively. A start the work and they do this work in alternate days. In how many days will this work be completed ?

A, B and C can complete a piece of work in 10 days, 20 days and 25 days, respectively. If they tak 40 days to complete a piece of work, then in how many days can C alone complete the work ?

X, Y and Z can complete a piece of work in 8, 20 and 25 days respectively. Working together, they will complete the same work in: