4 man can complete a piece of work in 2 ...

4 man can complete a piece of work in 2 days. 4 wonen can
complete the same piece of work in 4 days whereas 5 children
can complete the same piece of work in 4 days. If, 2 men, 4
women and 10 children work together, in how many days
can the work be completed ?

A

1 day

B

3 days

C

2 days

D

4 days

Text Solution

Verified by Experts

The correct Answer is:
(a)

`4xx 2` men= `4xx4` women `= 5xx4` chidren
`rArr 2 ` men = 4 women = 5 children
`therefore` 2 men + 4 women + 10 children
= 20 children
`therefore M_(1)D_(1) =M_(2)D_(2)`
`rArr5xx4=20xxD_(2) rArr D_(2)=1 day`
Promotional Banner

Topper's Solved these Questions

  • TIME , SPEED & DISTANCE (BOAT & STREAM)

    IBPS & SBI PREVIOUS YEAR PAPER|Exercise Question|91 Videos

Similar Questions

Explore conceptually related problems

15 men can complete a piece of work in 32 days. How many men can complete the work in 12 days ?

If 40 men complete a piece of work in 5 days, then 80 man can complete the same piece of work in _____.

In how many days 14 men can complete a piece of work? I. If 18 women can complete the same piece of work in 24 days II. If 28 children can complete the same piece of work in 56 days.

12 men can complete a piece of work in 16 days. In how many days will 4 men complete the same piece of work?

A alone can complete a piece of work in 6 days and B alone can complete the same piece of work in 12 days. In how many days can A and B together complete the same piece of work ?

21 men can complete a piece of work in 42/7 days. In how many days can 18 men complete the same piece of work?

10 men can complete a piece of work in 15 days and 15 women can complete the same work in 12 days. If all the 10 men and 15 women work together, in how many days will the work get completed?

IBPS & SBI PREVIOUS YEAR PAPER-TIME AND WORK/ PIPES AND CISTERNS-OPTION TYPE
  1. 4 man can complete a piece of work in 2 days. 4 wonen can complete t...

    Text Solution

    |

  2. 6 women alone can complete a piece of work in 10 days, whereas 10 ch...

    Text Solution

    |

  3. Six wome and 10 children together take six days to complete a piece ...

    Text Solution

    |

  4. 4 women and 12 children together take four days to complete a piece ...

    Text Solution

    |

  5. 2 women and 10 children together take 8 days to complete a piece of ...

    Text Solution

    |

  6. A can do a picec of work in 10 days and B is 25% more efficient than...

    Text Solution

    |

  7. A factory produces 1514 items in 3 days. How many items will they pr...

    Text Solution

    |

  8. 9 women con complete a piece of work in 19 days. How many days will ...

    Text Solution

    |

  9. 12 men alone can complete a piece of work in 6 days. Whereas 10 men ...

    Text Solution

    |

  10. A juice centre requires 35 dozen guavas for 28 days. How many dozen...

    Text Solution

    |

  11. A and B together can complete a particular task in 8 days. If B alon...

    Text Solution

    |

  12. Two pipes can fill a tank in 10 h and 16 h respectively. A third pip...

    Text Solution

    |

  13. 56 workers canfinish a piece of work in 14 days. If the work is to b...

    Text Solution

    |

  14. A alone can make 100 baskets in 6 days and B alone can make 100 bask...

    Text Solution

    |

  15. 8 men and 4 women together can complete a piece of work in 6 days. T...

    Text Solution

    |

  16. If a certain number of workmen can do a piece of work in 25 hours, ...

    Text Solution

    |

  17. Pipes A and B can fill a tank in 5 and 6 hours, respectively. Pipe C ...

    Text Solution

    |

  18. A and B together can do a piece of work in 6 days. If A can alone do...

    Text Solution

    |

  19. A tap can empty a tank in 30 minutes. A second tap can empty it in 4...

    Text Solution

    |

  20. A contract is to be completed in 46 days and 117 men were set to wo...

    Text Solution

    |