A contract is to be completed in 46 days...

A contract is to be completed in 46 days and 117 men were set to work, each working 8 hours a day. After 233 days, `4/7` of the work is completed. How many additional men may be employed so that the work may be completed in time, each man now working 9 hours a day? `80` b. `82` c. `81` d. `83`

A

80

B

81

C

82

D

83

Text Solution

Verified by Experts

The correct Answer is:
(b)

Let `x` additional men employed.
117 men were supposed to finish the whole work in
`46xx8= 368` hours.
But 117 men complete `4/7` of the work in `33 xx 8 `
= 264 hours
`therefore` 117 men could complete the work in 462 hours.
Now `(117 + x)` men are supposed to do `3/7` of the work,
working 9 hours a day, in `13xx 9 = 117` hours, so as to
finish the work in time.
i.e. `(117 + x )` men are supposed to complete the whole
work in `117 xx 7/3 = 273` hours.
`therefore (117+ x) xx 273 = 117 xx 462`
`rArr (117 + x)xx 7 = 3 xx 462`
`rArr x+ 117 = 3 xx 66 = 198 rArr x = 81`
`therefore` Required number of additional men to finish the
work in time = 81.
Promotional Banner

Topper's Solved these Questions

  • TIME , SPEED & DISTANCE (BOAT & STREAM)

    IBPS & SBI PREVIOUS YEAR PAPER|Exercise Question|91 Videos
IBPS & SBI PREVIOUS YEAR PAPER-TIME AND WORK/ PIPES AND CISTERNS-OPTION TYPE
  1. A and B together can do a piece of work in 6 days. If A can alone do...

    Text Solution

    |

  2. A tap can empty a tank in 30 minutes. A second tap can empty it in 4...

    Text Solution

    |

  3. A contract is to be completed in 46 days and 117 men were set to wo...

    Text Solution

    |

  4. Two pipes A and B can fill a cistern in 30 minutes and 40 minutes re...

    Text Solution

    |

  5. Two workers A and B working together completed a job in 5 days. If A...

    Text Solution

    |

  6. Pipes A can fill a tank in 30 minutes while pipe B can fill it in 45 ...

    Text Solution

    |

  7. A can build up a wall in 8 days while B can break it in 3 days, A ha...

    Text Solution

    |

  8. 12 men can finish a project in 20 days. 18 women can finish the same...

    Text Solution

    |

  9. Ais twice as efficient as B.B started the work and after 4 days A jo...

    Text Solution

    |

  10. Tow boy can do a piece of work in ten days. Three girls can do the s...

    Text Solution

    |

  11. A and B undertake to complete a piece of work for Rupees 1200. A can...

    Text Solution

    |

  12. A Works twice as fast as B. If B can complete a work in 24 days inde...

    Text Solution

    |

  13. A is thrice as efficient as B and hence completes a work in 40 days ...

    Text Solution

    |

  14. If one man or three women of five boys can do a piece of work in 46 ...

    Text Solution

    |

  15. Four examiners can examine a certain number of answer papers in 10 d...

    Text Solution

    |

  16. 24 man can complete a piece of work in 15 days. 2 days after the 24 ...

    Text Solution

    |

  17. A, B and C can alone complete a work in 15, 25 and 30 days respectiv...

    Text Solution

    |

  18. If P can do a work in 6 days and Q Can do the same work in 8 days. R...

    Text Solution

    |

  19. Three pipes P,Q and R can fill a tank in 12, 15 and 20 minutes respe...

    Text Solution

    |

  20. three pipes A, B, and C and fill the tank in 10 hours, 20 hours and ...

    Text Solution

    |