Home
Class 14
MATHS
Two workers A and B working together com...

Two workers A and B working together completed a job in 5
days. If A worked twice as efficiently as he actually did and
B worked 1/3 as efficiently as he actually did, the work would
have completed in 3 days. Fine the time for A to complete
the job alone.

A

`6 1/4` days

B

`5 3/4` days

C

5 days

D

3 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's denote the time taken by worker A to complete the job alone as \( A \) days and the time taken by worker B to complete the job alone as \( B \) days. ### Step 1: Set up the equations based on the given information. From the problem, we know that A and B together complete the job in 5 days. Therefore, their combined work rate can be expressed as: \[ \frac{1}{A} + \frac{1}{B} = \frac{1}{5} \] ### Step 2: Analyze the second condition. If A worked twice as efficiently, he would complete the job in \( \frac{A}{2} \) days. If B worked one-third as efficiently, he would take \( 3B \) days to complete the job. Thus, their combined work rate under these new conditions can be expressed as: \[ \frac{2}{A} + \frac{1}{3B} = \frac{1}{3} \] ### Step 3: Rewrite the equations. Now we have two equations: 1. \(\frac{1}{A} + \frac{1}{B} = \frac{1}{5}\) (Equation 1) 2. \(\frac{2}{A} + \frac{1}{3B} = \frac{1}{3}\) (Equation 2) ### Step 4: Solve Equation 1 for \(\frac{1}{B}\). From Equation 1, we can express \(\frac{1}{B}\) in terms of \(\frac{1}{A}\): \[ \frac{1}{B} = \frac{1}{5} - \frac{1}{A} \] ### Step 5: Substitute \(\frac{1}{B}\) into Equation 2. Substituting \(\frac{1}{B}\) into Equation 2 gives: \[ \frac{2}{A} + \frac{1}{3\left(\frac{1}{5} - \frac{1}{A}\right)} = \frac{1}{3} \] ### Step 6: Simplify the equation. To simplify the second term: \[ \frac{1}{3\left(\frac{1}{5} - \frac{1}{A}\right)} = \frac{1}{3} \cdot \frac{5A}{A - 5} \] Thus, our equation becomes: \[ \frac{2}{A} + \frac{5A}{3(A - 5)} = \frac{1}{3} \] ### Step 7: Clear the fractions by multiplying through by \( 3A(A - 5) \). Multiplying through by \( 3A(A - 5) \) gives: \[ 6(A - 5) + 5A^2 = A(A - 5) \] ### Step 8: Rearranging the equation. Expanding and rearranging gives: \[ 6A - 30 + 5A^2 = A^2 - 5A \] \[ 4A^2 + 11A - 30 = 0 \] ### Step 9: Solve the quadratic equation. Using the quadratic formula \( A = \frac{-b \pm \sqrt{b^2 - 4ac}}{2a} \): \[ A = \frac{-11 \pm \sqrt{11^2 - 4 \cdot 4 \cdot (-30)}}{2 \cdot 4} \] \[ A = \frac{-11 \pm \sqrt{121 + 480}}{8} \] \[ A = \frac{-11 \pm \sqrt{601}}{8} \] ### Step 10: Calculate the positive root. Since time cannot be negative, we take the positive root: \[ A = \frac{-11 + \sqrt{601}}{8} \] ### Final Answer: Thus, the time taken by worker A to complete the job alone is approximately \( 25/4 \) days or 6.25 days.

To solve the problem step by step, let's denote the time taken by worker A to complete the job alone as \( A \) days and the time taken by worker B to complete the job alone as \( B \) days. ### Step 1: Set up the equations based on the given information. From the problem, we know that A and B together complete the job in 5 days. Therefore, their combined work rate can be expressed as: \[ \frac{1}{A} + \frac{1}{B} = \frac{1}{5} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME , SPEED & DISTANCE (BOAT & STREAM)

    IBPS & SBI PREVIOUS YEAR PAPER|Exercise Question|91 Videos
IBPS & SBI PREVIOUS YEAR PAPER-TIME AND WORK/ PIPES AND CISTERNS-OPTION TYPE
  1. A contract is to be completed in 46 days and 117 men were set to wo...

    Text Solution

    |

  2. Two pipes A and B can fill a cistern in 30 minutes and 40 minutes re...

    Text Solution

    |

  3. Two workers A and B working together completed a job in 5 days. If A...

    Text Solution

    |

  4. Pipes A can fill a tank in 30 minutes while pipe B can fill it in 45 ...

    Text Solution

    |

  5. A can build up a wall in 8 days while B can break it in 3 days, A ha...

    Text Solution

    |

  6. 12 men can finish a project in 20 days. 18 women can finish the same...

    Text Solution

    |

  7. Ais twice as efficient as B.B started the work and after 4 days A jo...

    Text Solution

    |

  8. Tow boy can do a piece of work in ten days. Three girls can do the s...

    Text Solution

    |

  9. A and B undertake to complete a piece of work for Rupees 1200. A can...

    Text Solution

    |

  10. A Works twice as fast as B. If B can complete a work in 24 days inde...

    Text Solution

    |

  11. A is thrice as efficient as B and hence completes a work in 40 days ...

    Text Solution

    |

  12. If one man or three women of five boys can do a piece of work in 46 ...

    Text Solution

    |

  13. Four examiners can examine a certain number of answer papers in 10 d...

    Text Solution

    |

  14. 24 man can complete a piece of work in 15 days. 2 days after the 24 ...

    Text Solution

    |

  15. A, B and C can alone complete a work in 15, 25 and 30 days respectiv...

    Text Solution

    |

  16. If P can do a work in 6 days and Q Can do the same work in 8 days. R...

    Text Solution

    |

  17. Three pipes P,Q and R can fill a tank in 12, 15 and 20 minutes respe...

    Text Solution

    |

  18. three pipes A, B, and C and fill the tank in 10 hours, 20 hours and ...

    Text Solution

    |

  19. A and B can do a piece of work in 24 and 30 days respectively. Both ...

    Text Solution

    |

  20. Three pipe P, Q and R can fill a tank in 12 minutes, 18 minutes and ...

    Text Solution

    |