12 men can finish a project in 20 days. ...

12 men can finish a project in 20 days. 18 women can finish
the same project in 16 days and 24 children can finish it in 18
days. 8 women and 16 children worked for 9 days and then
left. In how many will 10 men coplete the remaining project ?

A

`10 1/2`

B

10

C

9

D

`11 1/2`

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first determine the work done by men, women, and children, and then calculate how long it will take for 10 men to complete the remaining work after 8 women and 16 children have worked for 9 days. ### Step 1: Calculate the work done by men, women, and children 1. **Work done by 12 men in 20 days**: - Total work = Number of men × Number of days = 12 men × 20 days = 240 man-days. 2. **Work done by 18 women in 16 days**: - Total work = Number of women × Number of days = 18 women × 16 days = 288 woman-days. 3. **Work done by 24 children in 18 days**: - Total work = Number of children × Number of days = 24 children × 18 days = 432 child-days.

To solve the problem step by step, we will first determine the work done by men, women, and children, and then calculate how long it will take for 10 men to complete the remaining work after 8 women and 16 children have worked for 9 days. ### Step 1: Calculate the work done by men, women, and children 1. **Work done by 12 men in 20 days**: - Total work = Number of men × Number of days = 12 men × 20 days = 240 man-days. 2. **Work done by 18 women in 16 days**: ...
Promotional Banner

Topper's Solved these Questions

  • TIME , SPEED & DISTANCE (BOAT & STREAM)

    IBPS & SBI PREVIOUS YEAR PAPER|Exercise Question|91 Videos

Similar Questions

Explore conceptually related problems

If 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.

6 men can complete a piece of work in 12 days, 8 women can complete the same piece of work in 18 days and 18 children can do it in 10 days. 4 men, 12 women and 20 children do the work for 2 days. If the remaining work be completed by men only in 1 day, how many men will be required? 36 b. 24 c. 18 d. cannot be determined

10 men can finish a piece of work in 10 days, whereas 12 women can finish it in 10 days. If 15 men and 6 women undertake to complete the work, how many days they will take to complete it ?

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

3 men can do a piece of work in 18 days. 6 children can also do that work in 18 days. 4 men and 4 children together will finish the work in how many days?

If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

IBPS & SBI PREVIOUS YEAR PAPER-TIME AND WORK/ PIPES AND CISTERNS-OPTION TYPE
  1. Pipes A can fill a tank in 30 minutes while pipe B can fill it in 45 ...

    Text Solution

    |

  2. A can build up a wall in 8 days while B can break it in 3 days, A ha...

    Text Solution

    |

  3. 12 men can finish a project in 20 days. 18 women can finish the same...

    Text Solution

    |

  4. Ais twice as efficient as B.B started the work and after 4 days A jo...

    Text Solution

    |

  5. Tow boy can do a piece of work in ten days. Three girls can do the s...

    Text Solution

    |

  6. A and B undertake to complete a piece of work for Rupees 1200. A can...

    Text Solution

    |

  7. A Works twice as fast as B. If B can complete a work in 24 days inde...

    Text Solution

    |

  8. A is thrice as efficient as B and hence completes a work in 40 days ...

    Text Solution

    |

  9. If one man or three women of five boys can do a piece of work in 46 ...

    Text Solution

    |

  10. Four examiners can examine a certain number of answer papers in 10 d...

    Text Solution

    |

  11. 24 man can complete a piece of work in 15 days. 2 days after the 24 ...

    Text Solution

    |

  12. A, B and C can alone complete a work in 15, 25 and 30 days respectiv...

    Text Solution

    |

  13. If P can do a work in 6 days and Q Can do the same work in 8 days. R...

    Text Solution

    |

  14. Three pipes P,Q and R can fill a tank in 12, 15 and 20 minutes respe...

    Text Solution

    |

  15. three pipes A, B, and C and fill the tank in 10 hours, 20 hours and ...

    Text Solution

    |

  16. A and B can do a piece of work in 24 and 30 days respectively. Both ...

    Text Solution

    |

  17. Three pipe P, Q and R can fill a tank in 12 minutes, 18 minutes and ...

    Text Solution

    |

  18. Pipes A and B can fill a cistern in 15 hours together. But if these ...

    Text Solution

    |

  19. A, b and C can alone complete a work in 10, 12 and 15 days respectiv...

    Text Solution

    |

  20. There are 4 filling pipes and 3 emptying pipes capable of filling an...

    Text Solution

    |