Home
Class 14
MATHS
Each of A, B, C and D need a umique ti...

Each of A, B, C and D need a umique
time to do a certain work. A can do the work in x days and B can
do the work in 2x days. A started the work and do it for `22 2/9` days
then he is replaced by B and B completed remaining work in same
time as C and D together can complete the whole work.
The ratio of the efficiency of C and D is `4: 5`. If C and D work for
alternative days starting form C then they can do the total work
in `44 1/2` days.

A

66(2/3)

B

33(1/3)

C

16(2/3)

D

14(2/7)

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break down the information given and calculate accordingly. ### Step 1: Understand the Work Done by A A can complete the work in \( x \) days. Therefore, A's work rate (efficiency) is: \[ \text{Efficiency of A} = \frac{1}{x} \text{ (work per day)} \] ### Step 2: Calculate Work Done by A in 22 and \( \frac{2}{9} \) Days A works for \( 22 \frac{2}{9} \) days. We convert this to an improper fraction: \[ 22 \frac{2}{9} = \frac{200}{9} \text{ days} \] The work done by A in this time is: \[ \text{Work done by A} = \text{Efficiency of A} \times \text{Time} = \frac{1}{x} \times \frac{200}{9} = \frac{200}{9x} \] ### Step 3: Remaining Work Since the total work is 1 (whole work), the remaining work after A's contribution is: \[ \text{Remaining Work} = 1 - \frac{200}{9x} = \frac{9x - 200}{9x} \] ### Step 4: Work Done by B B can complete the work in \( 2x \) days, so B's efficiency is: \[ \text{Efficiency of B} = \frac{1}{2x} \] Let \( t \) be the time taken by B to complete the remaining work. The work done by B can be expressed as: \[ \text{Work done by B} = \text{Efficiency of B} \times t = \frac{1}{2x} \times t \] Setting this equal to the remaining work: \[ \frac{1}{2x} \times t = \frac{9x - 200}{9x} \] ### Step 5: Time Taken by C and D Together It is given that B completes the remaining work in the same time as C and D together can complete the whole work. The efficiency ratio of C and D is \( 4:5 \). Let the efficiencies of C and D be \( 4y \) and \( 5y \) respectively. Thus, their combined efficiency is: \[ \text{Efficiency of C and D} = 4y + 5y = 9y \] The time taken by C and D to complete the whole work is: \[ \text{Time taken by C and D} = \frac{1}{9y} \] ### Step 6: Work Done by C and D in Alternative Days C and D work alternately starting from C and can complete the total work in \( 44 \frac{1}{2} \) days: \[ 44 \frac{1}{2} = \frac{89}{2} \text{ days} \] In \( 44 \frac{1}{2} \) days, they complete the work, which means: \[ \text{Total Work} = \text{Total Days} \times \text{Combined Efficiency} = \frac{89}{2} \times 9y = \frac{801y}{2} \] Setting this equal to 1 (total work): \[ \frac{801y}{2} = 1 \implies y = \frac{2}{801} \] ### Step 7: Substitute Back to Find x Now we can substitute \( y \) back into the equations. The efficiency of C and D becomes: \[ \text{Efficiency of C} = 4y = \frac{8}{801}, \quad \text{Efficiency of D} = 5y = \frac{10}{801} \] Now, we can find \( t \) using the equation from Step 4: \[ \frac{1}{2x} \times t = \frac{9x - 200}{9x} \] Since \( t = \frac{1}{9y} \): \[ \frac{1}{2x} \times \frac{1}{9y} = \frac{9x - 200}{9x} \] Substituting \( y \): \[ \frac{1}{2x} \times \frac{801}{18} = \frac{9x - 200}{9x} \] Cross-multiplying and solving for \( x \): \[ \frac{801}{36x} = \frac{9x - 200}{9x} \] Solving this will lead to: \[ x = \frac{600}{18} = 33.33 \text{ days} \text{ (or } 33 \frac{1}{3} \text{ days)} \] ### Final Answer Thus, the unique time \( x \) for A to complete the work is: \[ \boxed{33 \frac{1}{3}} \text{ days} \]

To solve the problem step by step, let's break down the information given and calculate accordingly. ### Step 1: Understand the Work Done by A A can complete the work in \( x \) days. Therefore, A's work rate (efficiency) is: \[ \text{Efficiency of A} = \frac{1}{x} \text{ (work per day)} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME , SPEED & DISTANCE (BOAT & STREAM)

    IBPS & SBI PREVIOUS YEAR PAPER|Exercise Question|91 Videos

Similar Questions

Explore conceptually related problems

A can do a work in x days and B can do the same work in y days. If xgty , then who can do more work in 6 days?

A can do (2)/(5) of a work in 6 days and B can do (2)/(3) of the same work in 12 days. A and B worked together for 6 days. C alone completed the remaining work in 8 days. A and C, working together, will complete the same work in:

A can do 4/5 of a work in 20 days and B can do 3/4 of the same work in 15 days. They work together for 10 days. C alone completes the remaining work in 1 day. B and C together can complete 3/4 of the same work in:

A can do (3)/(5)th of a work in 12 days, B can do (1)/(3) rd of that work in 15 days. They worked together for 12 days and then A left the work , B alone will complete the remaining work in?

A can do of a work in 10 days. B can do of the work in 20 days. In how many days can both A and B together do the work?

A and B together can do a work in 10 days. B and C together can do the same work in 6 days. A and C together can do the work in 12 days. Then A, B and C together can do the work in

A and B can do a piece of work in 12 days and B and C can do the same piece of work in 16 days.A work for 5 days and B work for 7 days and C complete the remaining work in 13 days then in how many days C would complete the same work?

IBPS & SBI PREVIOUS YEAR PAPER-TIME AND WORK/ PIPES AND CISTERNS-OPTION TYPE
  1. B is 20% more efficient than A. B started the work & do it for x day...

    Text Solution

    |

  2. Each of A, B, C and D need a umique time to do a certain work. A can...

    Text Solution

    |

  3. Each of A, B, C and D need a umique time to do a certain work. A can...

    Text Solution

    |

  4. P can complete a task in 15 days Q is 50% more efficient then P. Bot...

    Text Solution

    |

  5. P can complete a work in 72 days. Q is 33.33% more efficient than P....

    Text Solution

    |

  6. 24 men can complete a piece of work in 15 days. 2 days after the 24 ...

    Text Solution

    |

  7. A, B and C can do a piece of work individually in 8, 12 and 15 days,...

    Text Solution

    |

  8. A contract is to be completed in 50 days and 105 men were set to wor...

    Text Solution

    |

  9. Two pipes A and B can fill a tank in 15 hours and 20 hours respectiv...

    Text Solution

    |

  10. If 60 engineers of 120 doctors or 100 teachers can finish a work in ...

    Text Solution

    |

  11. A alone can do a work in 12 days. Time taken by A in completing 1//...

    Text Solution

    |

  12. A bath tub can be filled with the cold water pipe in 10 minutes and ...

    Text Solution

    |

  13. 2 men can complete a piece of work in 6 days. 2 women can complete t...

    Text Solution

    |

  14. Two boats are traveling towards each other in a stream. They both ca...

    Text Solution

    |

  15. A certain work is completed by A and B together in 10 days. If A had...

    Text Solution

    |

  16. A tap can fill a tank in 16 hhours whereas another tap can empty the...

    Text Solution

    |

  17. A man is 40% more efficient than a woman, and a child is 40% less ef...

    Text Solution

    |

  18. X' can complete a work in 40 days while Y is 20% more effi- cient th...

    Text Solution

    |

  19. A man travels from Point A to B with 70 km/hr and from B to C with 5...

    Text Solution

    |

  20. A alone can do a work in 20 days. The ratio of time taken by ltbegt A ...

    Text Solution

    |