Home
Class 14
MATHS
P can complete a task in 15 days Q is 50...

P can complete a task in 15 days Q is 50% more efficient
then P. Both P and Q started working together on the
task and after few day Q lift task and P finished the
remaining 1/3of the given work. For how many days P and Q worled together.

A

3

B

5

C

4

D

6

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will analyze the work done by P and Q and determine how many days they worked together. ### Step 1: Determine the work rate of P P can complete the task in 15 days. Therefore, the work rate of P is: \[ \text{Work rate of P} = \frac{1}{15} \text{ (work per day)} \] ### Step 2: Determine the work rate of Q Q is 50% more efficient than P. This means Q can do 1.5 times the work that P can do in a day. Thus, the work rate of Q is: \[ \text{Work rate of Q} = 1.5 \times \frac{1}{15} = \frac{1.5}{15} = \frac{1}{10} \text{ (work per day)} \] ### Step 3: Calculate the combined work rate of P and Q When P and Q work together, their combined work rate is: \[ \text{Combined work rate} = \text{Work rate of P} + \text{Work rate of Q} = \frac{1}{15} + \frac{1}{10} \] To add these fractions, we need a common denominator, which is 30: \[ \text{Combined work rate} = \frac{2}{30} + \frac{3}{30} = \frac{5}{30} = \frac{1}{6} \text{ (work per day)} \] ### Step 4: Determine the total work done Since P finished the remaining \( \frac{1}{3} \) of the work alone, it means that together they completed \( 1 - \frac{1}{3} = \frac{2}{3} \) of the work. ### Step 5: Calculate the time taken by P and Q to complete \( \frac{2}{3} \) of the work Let \( x \) be the number of days P and Q worked together. The amount of work they completed together in \( x \) days is: \[ \text{Work done together} = x \times \frac{1}{6} \] Setting this equal to \( \frac{2}{3} \): \[ x \times \frac{1}{6} = \frac{2}{3} \] ### Step 6: Solve for \( x \) To solve for \( x \), we can multiply both sides by 6: \[ x = \frac{2}{3} \times 6 = 4 \] ### Conclusion P and Q worked together for **4 days**. ---

To solve the problem step by step, we will analyze the work done by P and Q and determine how many days they worked together. ### Step 1: Determine the work rate of P P can complete the task in 15 days. Therefore, the work rate of P is: \[ \text{Work rate of P} = \frac{1}{15} \text{ (work per day)} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME , SPEED & DISTANCE (BOAT & STREAM)

    IBPS & SBI PREVIOUS YEAR PAPER|Exercise Question|91 Videos
IBPS & SBI PREVIOUS YEAR PAPER-TIME AND WORK/ PIPES AND CISTERNS-OPTION TYPE
  1. Each of A, B, C and D need a umique time to do a certain work. A can...

    Text Solution

    |

  2. Each of A, B, C and D need a umique time to do a certain work. A can...

    Text Solution

    |

  3. P can complete a task in 15 days Q is 50% more efficient then P. Bot...

    Text Solution

    |

  4. P can complete a work in 72 days. Q is 33.33% more efficient than P....

    Text Solution

    |

  5. 24 men can complete a piece of work in 15 days. 2 days after the 24 ...

    Text Solution

    |

  6. A, B and C can do a piece of work individually in 8, 12 and 15 days,...

    Text Solution

    |

  7. A contract is to be completed in 50 days and 105 men were set to wor...

    Text Solution

    |

  8. Two pipes A and B can fill a tank in 15 hours and 20 hours respectiv...

    Text Solution

    |

  9. If 60 engineers of 120 doctors or 100 teachers can finish a work in ...

    Text Solution

    |

  10. A alone can do a work in 12 days. Time taken by A in completing 1//...

    Text Solution

    |

  11. A bath tub can be filled with the cold water pipe in 10 minutes and ...

    Text Solution

    |

  12. 2 men can complete a piece of work in 6 days. 2 women can complete t...

    Text Solution

    |

  13. Two boats are traveling towards each other in a stream. They both ca...

    Text Solution

    |

  14. A certain work is completed by A and B together in 10 days. If A had...

    Text Solution

    |

  15. A tap can fill a tank in 16 hhours whereas another tap can empty the...

    Text Solution

    |

  16. A man is 40% more efficient than a woman, and a child is 40% less ef...

    Text Solution

    |

  17. X' can complete a work in 40 days while Y is 20% more effi- cient th...

    Text Solution

    |

  18. A man travels from Point A to B with 70 km/hr and from B to C with 5...

    Text Solution

    |

  19. A alone can do a work in 20 days. The ratio of time taken by ltbegt A ...

    Text Solution

    |

  20. R is 1.5 times as efficient as that of P, and Q takes half time as c...

    Text Solution

    |