P can complete a work in 72 days. Q is 3...

P can complete a work in 72 days. Q is 33.33% more efficient
than P. In how many days both complete the work if they
work on alternate days starting with P?

A

56 days

B

60 days

C

62 days

D

none of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Determine the work done by P and Q P can complete the work in 72 days. Therefore, P's work rate is: \[ \text{Work rate of P} = \frac{1}{72} \text{ (work per day)} \] Q is 33.33% more efficient than P. This means Q can do more work in a day compared to P. To find Q's efficiency, we can calculate it as follows: \[ \text{Efficiency of Q} = \text{Efficiency of P} \times \left(1 + \frac{33.33}{100}\right) = \frac{1}{72} \times \frac{4}{3} = \frac{4}{216} = \frac{1}{54} \] So, Q can complete the work in 54 days. ### Step 2: Calculate the total work in terms of units To find the total work, we can take the LCM of the days taken by P and Q: - Days taken by P = 72 - Days taken by Q = 54 The LCM of 72 and 54 is 216. Therefore, the total work can be considered as 216 units. ### Step 3: Calculate the work done by P and Q in one cycle of two days In one day: - Work done by P = \(\frac{216}{72} = 3\) units - Work done by Q = \(\frac{216}{54} = 4\) units In two days (one day of P and one day of Q): \[ \text{Total work done in 2 days} = 3 + 4 = 7 \text{ units} \] ### Step 4: Calculate how many complete cycles can be done To find out how many complete cycles can be done in 216 units: \[ \text{Number of complete cycles} = \frac{216}{7} \approx 30.857 \] This means they can complete 30 full cycles (60 days) and then we will have some work left. ### Step 5: Calculate the work done in 60 days In 60 days, the total work done is: \[ \text{Total work done in 60 days} = 30 \times 7 = 210 \text{ units} \] ### Step 6: Calculate the remaining work The remaining work after 60 days is: \[ \text{Remaining work} = 216 - 210 = 6 \text{ units} \] ### Step 7: Determine who will do the remaining work On the 61st day, P will work. P can do 3 units of work in one day. Since the remaining work is 6 units, P will do 3 units on the 61st day, leaving 3 units. On the 62nd day, Q will work. Q can do 4 units of work in one day. Q will complete the remaining 3 units on the 62nd day. ### Step 8: Calculate the total days taken Total days taken: - 60 days for the complete cycles - 1 day for P (61st day) - 1 day for Q (62nd day) Thus, the total days taken is: \[ \text{Total days} = 60 + 1 + 1 = 62 \text{ days} \] ### Final Answer Both P and Q can complete the work in **62 days**. ---

To solve the problem step by step, let's break it down: ### Step 1: Determine the work done by P and Q P can complete the work in 72 days. Therefore, P's work rate is: \[ \text{Work rate of P} = \frac{1}{72} \text{ (work per day)} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME , SPEED & DISTANCE (BOAT & STREAM)

    IBPS & SBI PREVIOUS YEAR PAPER|Exercise Question|91 Videos
IBPS & SBI PREVIOUS YEAR PAPER-TIME AND WORK/ PIPES AND CISTERNS-OPTION TYPE
  1. Each of A, B, C and D need a umique time to do a certain work. A can...

    Text Solution

    |

  2. P can complete a task in 15 days Q is 50% more efficient then P. Bot...

    Text Solution

    |

  3. P can complete a work in 72 days. Q is 33.33% more efficient than P....

    Text Solution

    |

  4. 24 men can complete a piece of work in 15 days. 2 days after the 24 ...

    Text Solution

    |

  5. A, B and C can do a piece of work individually in 8, 12 and 15 days,...

    Text Solution

    |

  6. A contract is to be completed in 50 days and 105 men were set to wor...

    Text Solution

    |

  7. Two pipes A and B can fill a tank in 15 hours and 20 hours respectiv...

    Text Solution

    |

  8. If 60 engineers of 120 doctors or 100 teachers can finish a work in ...

    Text Solution

    |

  9. A alone can do a work in 12 days. Time taken by A in completing 1//...

    Text Solution

    |

  10. A bath tub can be filled with the cold water pipe in 10 minutes and ...

    Text Solution

    |

  11. 2 men can complete a piece of work in 6 days. 2 women can complete t...

    Text Solution

    |

  12. Two boats are traveling towards each other in a stream. They both ca...

    Text Solution

    |

  13. A certain work is completed by A and B together in 10 days. If A had...

    Text Solution

    |

  14. A tap can fill a tank in 16 hhours whereas another tap can empty the...

    Text Solution

    |

  15. A man is 40% more efficient than a woman, and a child is 40% less ef...

    Text Solution

    |

  16. X' can complete a work in 40 days while Y is 20% more effi- cient th...

    Text Solution

    |

  17. A man travels from Point A to B with 70 km/hr and from B to C with 5...

    Text Solution

    |

  18. A alone can do a work in 20 days. The ratio of time taken by ltbegt A ...

    Text Solution

    |

  19. R is 1.5 times as efficient as that of P, and Q takes half time as c...

    Text Solution

    |

  20. Efficiency of Q is two times more than efficiency of P. Both started...

    Text Solution

    |