Home
Class 14
MATHS
A alone can do a work in 20 days. The ra...

A alone can do a work in 20 days. The ratio of time taken by ltbegt A and B to do the same work is 4:3 Then, find in how many
days both will complete the work together ?

A

7.25 days

B

12 days

C

8 days

D

8.5 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will follow these steps: ### Step 1: Determine the work done by A in one day. A can complete the work in 20 days. Therefore, the amount of work done by A in one day is: \[ \text{Work done by A in one day} = \frac{1}{20} \] ### Step 2: Find the time taken by B to complete the work. The ratio of the time taken by A and B is given as 4:3. Let the time taken by A be \(4x\) and the time taken by B be \(3x\). Since A takes 20 days to complete the work, we can set up the equation: \[ 4x = 20 \implies x = 5 \] Now, substituting \(x\) back to find the time taken by B: \[ \text{Time taken by B} = 3x = 3 \times 5 = 15 \text{ days} \] ### Step 3: Determine the work done by B in one day. Now, we can find the work done by B in one day: \[ \text{Work done by B in one day} = \frac{1}{15} \] ### Step 4: Calculate the combined work done by A and B in one day. To find the total work done by both A and B together in one day, we add their individual work rates: \[ \text{Combined work done in one day} = \frac{1}{20} + \frac{1}{15} \] To add these fractions, we need a common denominator. The least common multiple of 20 and 15 is 60. Thus, we convert the fractions: \[ \frac{1}{20} = \frac{3}{60}, \quad \frac{1}{15} = \frac{4}{60} \] Now, adding these: \[ \text{Combined work done in one day} = \frac{3}{60} + \frac{4}{60} = \frac{7}{60} \] ### Step 5: Calculate the total time taken by A and B to complete the work together. If A and B together can complete \(\frac{7}{60}\) of the work in one day, then the total time taken to complete 1 whole work is the reciprocal of this rate: \[ \text{Total time taken} = \frac{1}{\frac{7}{60}} = \frac{60}{7} \text{ days} \] ### Final Answer: Thus, A and B together will complete the work in \(\frac{60}{7}\) days, which is approximately 8.57 days. ---

To solve the problem, we will follow these steps: ### Step 1: Determine the work done by A in one day. A can complete the work in 20 days. Therefore, the amount of work done by A in one day is: \[ \text{Work done by A in one day} = \frac{1}{20} \] ...
Promotional Banner

Topper's Solved these Questions

  • TIME , SPEED & DISTANCE (BOAT & STREAM)

    IBPS & SBI PREVIOUS YEAR PAPER|Exercise Question|91 Videos
IBPS & SBI PREVIOUS YEAR PAPER-TIME AND WORK/ PIPES AND CISTERNS-OPTION TYPE
  1. A contract is to be completed in 50 days and 105 men were set to wor...

    Text Solution

    |

  2. Two pipes A and B can fill a tank in 15 hours and 20 hours respectiv...

    Text Solution

    |

  3. If 60 engineers of 120 doctors or 100 teachers can finish a work in ...

    Text Solution

    |

  4. A alone can do a work in 12 days. Time taken by A in completing 1//...

    Text Solution

    |

  5. A bath tub can be filled with the cold water pipe in 10 minutes and ...

    Text Solution

    |

  6. 2 men can complete a piece of work in 6 days. 2 women can complete t...

    Text Solution

    |

  7. Two boats are traveling towards each other in a stream. They both ca...

    Text Solution

    |

  8. A certain work is completed by A and B together in 10 days. If A had...

    Text Solution

    |

  9. A tap can fill a tank in 16 hhours whereas another tap can empty the...

    Text Solution

    |

  10. A man is 40% more efficient than a woman, and a child is 40% less ef...

    Text Solution

    |

  11. X' can complete a work in 40 days while Y is 20% more effi- cient th...

    Text Solution

    |

  12. A man travels from Point A to B with 70 km/hr and from B to C with 5...

    Text Solution

    |

  13. A alone can do a work in 20 days. The ratio of time taken by ltbegt A ...

    Text Solution

    |

  14. R is 1.5 times as efficient as that of P, and Q takes half time as c...

    Text Solution

    |

  15. Efficiency of Q is two times more than efficiency of P. Both started...

    Text Solution

    |

  16. 8 men and 5 women together can complete a piece of work in 7 days and...

    Text Solution

    |

  17. A shopkeeper gives 10% discount on marked price of an article and ea...

    Text Solution

    |

  18. Raja and Baja working alone can do a work in 20 days and 15 days resp...

    Text Solution

    |

  19. Shahu can do a work in 18 days, Yash can do the same work in 24 days...

    Text Solution

    |

  20. Satish is 50% more efficient than Charan. They together start the wo...

    Text Solution

    |