A contractor undertakes to do a piece of...

A contractor undertakes to do a piece of work in 40 days. He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time. If he had not engaged the additional men, how many days behind the schedule the work should have been finished? a. `5` b. `\ 6` c. `7` d. `8`

Promotional Banner

Similar Questions

Explore conceptually related problems

A contractor undertakes to do a piece of work in 40 days.He engages 100 men at the beginning and 100 more after 35 days and completes the work in stipulated time.If he had not engaged the additional men,how many days behind the schedule the work should have been finished? a.5 b.backslash6 c.7 d.8

A builder decided to build a farmhouse in 45 days. He employed 150 men in the beginning and120 more after 30 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?

A builder decided to build a farmhouse in 45 days. He employed 106 men in the beginning and 53 more after 35 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behing schedule would it have been finished?

A builder decided to build a farmhouse in 20 days. He employed 40 men in the beginning and 20 more after 10 days and completed the construction in stipulated time. If he had not employed the additional men, how many days behind schedule would it have been finished?

24 men working at 8 hours per day can do a piece of work in 15 days. In how many days can 20 men working at 9 hours per day can complete the same work?

If 8 men can finish a piece of work in 40 days.then 10 men can finish it in 32 days.