40 men can finish a piece of work in 26 ...

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

Promotional Banner

Similar Questions

Explore conceptually related problems

If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?

If 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?

If 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?

36 men can do a piece of work in 7 days. How many men will do the same work in 42 days ?

4 men and 6 boys can finish a piece of work in 5 days while 3 men and 4 boys can finish it in 7 days , then the time taken by one man alone is

10 men can finish painting a wall in 8 days. How many more men will be needed if the painting work is to be finished in 4 days?

8 men can finish a piece of work in 15 hours.In how many hours can 20 men finish it?