Home
Class 10
MATHS
A contract on construction job specifies...

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows: Rs 200 for the first day, Rs 250 for the second day Rs 300 for the third day, etc., the penalty for each succeeding day being Rs 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days?

Promotional Banner

Similar Questions

Explore conceptually related problems

A contract on construction job specific a penalty for delay of completion beyond a certain date as follows : Rs. 200 for the first day, Rs.250 for the second day, Rs. 300 for the third day, etc., the penalty for each succeeding day being Rs. 50 more than for the preceding day. How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?

A contract on construction job specifies a penalty for delay of completionbeyond a certain data as follows: Rs 200 for the first day , Rs250 for the second day, Rs 300 for the third day , etc., the penalty for each succeeding day being Rs50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 30 days ?

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follow : Rs 500 for the first day , Rs 550 for the second day , Rs 600 for the third day , etc the penalty for each suceeding day being Rs 50 more than for the preceding day . How much money the contractor has to pay as penalty , if he has delayed the work by 50 days ?

A contract on construction job specifies a penalty for delay of completion beyond a certain date as follows : $200 for the first day, $250 for the second day, $ 300 for the third day, etc., the penalty for each succeeding day being $50 more than for the preceding day, How much money the contractor has to pay as penalty, if he has delayed the work by 30 days ?

A contract on construction job specifies a penalty for delay of completion beyond a certain days as follows: Rs. 180 for the first day, Rs. 200 for the second day, etc., the penalty for each succeeding day being Rs. 20 more than the preceding day. (i) How much money the contractor has to pay as penalty, if he has delayed the work by 15 days? (ii) For how many days has the contractor delayed the work if he paid Rs. 7400 as penalty?

A contract of construction job specifies a penalty for delay of completion beyond a certain date as follows:₹200 for the first day,₹250 for the second day,₹300 for the thrid day etc.the penalty for each succeeding day being ₹50 more than for the preceding day.How much does a delay of 30 days cost the contractor?

A contractor construction job specifies a penalty for delay of completion beyond a certain date as follow. Rs. 200 for the first day. The penalty for each succeeding day being Rs. 50 more than the preceding day. How much money does the contractor pay as penalty if he has delayed the work by 30 days?

A contract on construction job specifies a penalty for delay of completion beyond acertain date as follows: Rs 200 for Ist day,Rs.250 for second day,Rs.300 for thirdday and so on.If the contractor pays Rs 27750 as penalty, find the number of days forwhich the construction work is delayed.

A contract on construction job specifies a penalty for delay of completion beyond a certain date is as follows, ₹200 for 1st day, ₹250 for 2nd day, ₹300 for 3rd day and so on.If the contractor pays 27,750 as penalty,find the number of days for which the work is delayed.

A boy spends Rs. 10 on first day, Rs. 20 on second day, Rs. 40 on third day and so on. Find how much, in all, will he spend in 12 days ?