A contractor employed 30 men to do a pie...

A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? `1` b. `\ 1 1/4` c. `1 3/4` d. `1 1/2`

Promotional Banner

Similar Questions

Explore conceptually related problems

A contractor employed 30 men to do a piece of work in 38 days. After 25 days, he employed 5 men more and the work was finished one day earlier. How many days he would have been behind, if he had not employed additional men? .a. 1 b. \ 1 1/4 c. 1 3/4 d. 1 1/2

A team of 30 men is supposed to do a work in 38 days. After 25 days, 5 more men were employed and the work finished one day earlier.How many days would it have been delayed if 5 more men were not employed?

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

If 36 men can do a piece of work in 25 days, in how many days will 15 men do it?

72 men do a piece of work in 25 days. In how many days will 30 men do the same work ?

If 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?

8 men can do a piece of work in 15 days. Find in how many days will 10 men finish the same work.

8 men can do a work in 12 days. After 6 days of work, 4 more men were engaged to finish the work. In how many days would the remaining work be completed?