A can do a piece of work in 25 days and ...

A can do a piece of work in 25 days and B can finish it in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

Promotional Banner

Similar Questions

Explore conceptually related problems

A can do a piece of work in 25 days and B in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the remaining work ?

A can finish a piece of work in 15 days and B can do it in 10 days. They worked together for 2 days and then B goes away. In how many days will A finish the remaining work ?

A can do a work in 25 days and B can do the same work in 20 days. They work together for 5 days and then A goes away. In how many days will B finish the work?

A\ a n d\ B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

A\ a n d\ B can do a piece of work in 20 days and 15 days. They work together for 2 days and then A goes away. In how many days will B finish the remaining work?

A can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away. In how many days will A finish the remaining work?

A can do a piece of work in 40 days and B in 45 days.They work together for 10 days and then B goes away.In how many days will A finish the remaining work?

A can do a piece of work in 80 days and B in 100 days. They work together for first 20 days before B goes away. In how many days will A manage to finish the remaining work?

Deepak can do a piece of work in 25 days and Ashok can do the same work in 40 days.They work together for 5days and then Deepak goes away.In how many days will Ashok finish the remaining work?