If 40 men can finish a piece of work in 26 days, how many men will be required to finish it in 20 days?

Promotional Banner

Similar Questions

Explore conceptually related problems

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

40 men can finish a piece of work in 26 days. How many men will be needed to finish it in 16 days?

30 men can finish a piece of work in 28 days. How many days will be taken by 21 men to finish it?

If 40 men can finish a piece of work in 60 days. In how many days will 75 , men finish the same work ?

If 36 men can finish a piece of work in 35 days.how many days will 15 men take to do it ?

If 8 men can do a piece of work in 15 days, how many men are required to do the same piece of work in 10 days ?