Amar, Bhavan and Chetan can complete a j...

Amar, Bhavan and Chetan can complete a job in 24 days, 36 days, and 48 days, respectively. Amar, Bhavan and Chetan started it. After 6 days, Amar left. The order tow continued to work. Bhavanleft 15 days the comletion work. Bhava left 15 days, before the completeion of the job. Chetan comlete the remaining work. Find the total time teaken to complet the job . ( in days)

Promotional Banner

Similar Questions

Explore conceptually related problems

A, B and C can complete a piece of work in 27 days, 36 days, adn 45 days, respectively. B and C started the work. After 11 days. A joined them. If B left 12 days before its completion, in how many days will the work be completed?

A, B and C can complete a piece of work in 15, 30 and 40 days respectively. They started the work together and A left 2 days before the completion of the work and B left 4 days before the completion of the work. In how many days was the work completed?

A, B and C can individually complete a piece of work in 24 days, 15 days and 12 days. respectively. B and C started the work and worked for 3 days and left. The number of days required by A alone to complete the remaining work is :

M and N can complete a job in 18 days and 20 days, respectively. They worked on it on alternative days starting with M. Find the time taken to comlete it (in day)

A , B and C can do a piece of work in 24days,36 days and 108 days, respectively. They started the work together but A left 9 days after the start of the work and B left 3 days before the work was completed. For how many days did C work ?

A, B and C can individually complete a task in 24 days, 16 days and 32 days respectively. If A and C started the work and worked for 6 days and left, then the number of days required by B to complete the remaining task is :