Thirty men can do a piece of work in 16 ...

Thirty men can do a piece of work in 16 days working 8 hours a day. How many men are needed to complete another work, which is twice the first one, in 10 days working 12 working a day?
The following are the steps involved in solving the above problem. Arrange them in sequential order.
`M_(2)=(30xx16xx8xx2x)/(x xx12xx10)`
`(30xx16xx8)/(x)=(M_(2)xx12xx10)/(2x)`
`(M_(1)D_(1)H_(1))/(W_(1))=(M_(2)D_(2)H_(2))/(W_(2))`
`M_(2)=64`

Promotional Banner

Similar Questions

Explore conceptually related problems

A piece of work can be done by 16 men in 8 days working 12 hours a day. How many men are needed to complete another work, which is three times the first one, in 24 days working 8 hours a days ?

A piece of work can be done by 16 man in 8 days working 12 hours a day. How many men ar needed to complete another work,which is three times the first one, in 24n days working 8 hourse, a day?

Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?

Twelve men can do a piece of work in 15 days. How many men are required to complete a work which is three and a half times the original work in 10 days ?

12 men can do a piece of work in 24 days.How many days are needed to complete the work,if 8 men do this work? 28 b.36c.48d.52

90 men can complete a work in 24 days working 8 hours a day. How many men are working 8 hours a day. How many men are required to complete the same work in 18 days working 7(1)/(2) hours a day ?