A contractor employed 30 men to complete...

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only `20%` of the work is completed How many men should be increased so that the work will be completed in 25 days less than the scheduled time

Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the work How many extra days, than the scheduled time are required?

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the To complete the work on the scheduled time how many men he has to increase?

A contractor employed 30 men to complete the project in 100 days. But later on he realised that just after 25 days only 20% of the If the amount of work is also increased by 20% of the actual work, then how many extra days are required (m comparison with scheduled time) but the number of men remained constant

A contractor undertakes to make a mall in 60 days and he employs 30 men. After 30 days it is found that only one- third of the work is completed. How many extre men should he employ so that the work is completed on time?

90 men are engaged to do a piece of work in 40 days but it is found that in 25 days, 2/3 work is completed. How many men should be allowed to go off, so that the work may be finished in time?

A contractor undertakes to complete a road 360 m long in 120 days and employs 30 men for the work. After 60 days he finds that only 120 m length of the road has been made. How many more men should he employ so that the work may be completed in time ?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. A contractor employed 30 men to complete the project in 100 days. But ...

    Text Solution

    |

  2. A contractor employed 30 men to complete the project in 100 days. But ...

    Text Solution

    |

  3. A contractor employed 30 men to complete the project in 100 days. But ...

    Text Solution

    |

  4. 16 workers working 6 hours a day can build a wall of length 150 metres...

    Text Solution

    |

  5. 6 boys and 8 women finish a job in 6 days and 14 boys and 10 women fin...

    Text Solution

    |

  6. 6 men or 8 women can do a job in 10 days In how many days can 5 men an...

    Text Solution

    |

  7. 6 men and 8 women can do a job in 10'days. In how many days can 3 men ...

    Text Solution

    |

  8. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  9. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  10. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  11. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  12. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  13. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  14. A can complete a work in 15 days, B in 18 days. Find the time taken by...

    Text Solution

    |

  15. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  16. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  17. A can complete a work in 16 days, B in 12 days and C in l5 days. All o...

    Text Solution

    |

  18. A alone con finish a piece of work in 12 days and B alone can do it in...

    Text Solution

    |

  19. A can do a piece of work in 10 days, B can do it in 12 days and C can ...

    Text Solution

    |

  20. A can do a piece of work in 5 days, B can do it in 10 days. With the h...

    Text Solution

    |