6 men or 8 women can do a job in 10 days...

6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?

Text Solution

AI Generated Solution

Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

6 men and 8 women can do a job in 10'days. In how many days can 3 men and 4 women finish the same job working together?

12 men and 15 women can do a work in 6 days, and 6 men and 12 women can do it in 10 days, in how many days can 8 men and 10 women do the same work?

6 men and 9 women can do a piece of work in 4 days.4 men and 3 women can do it in 8 days. In how many days can 20 men and 6 women do the same work ?

6 men and 9 women can do a piece of work in 4 days.4 men and 3 women can do it in 8 days. In how many days can 20 men and 6 women do the same work ?

Six men and 4 women can do a piece of work in 32 days. Seven men and 12 women can do it in 18 days. In how many days can 18 men and 8 women do the same work, working together ?

Six men and 4 women can do a piece of work in 32 days. Seven men and 12 women can do it in 18 days. In how many days can 18 men and 8 women do the same work, working together ?

2 men and 7 women can do a piece of work in 14 days whereas 3 men and 8 women can do it in 11 days. In how many days 5 men and 4 women can do the same work?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. 16 workers working 6 hours a day can build a wall of length 150 metres...

    Text Solution

    |

  2. 6 boys and 8 women finish a job in 6 days and 14 boys and 10 women fin...

    Text Solution

    |

  3. 6 men or 8 women can do a job in 10 days In how many days can 5 men an...

    Text Solution

    |

  4. 6 men and 8 women can do a job in 10'days. In how many days can 3 men ...

    Text Solution

    |

  5. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  6. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  7. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  8. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  9. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  10. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  11. A can complete a work in 15 days, B in 18 days. Find the time taken by...

    Text Solution

    |

  12. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  13. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  14. A can complete a work in 16 days, B in 12 days and C in l5 days. All o...

    Text Solution

    |

  15. A alone con finish a piece of work in 12 days and B alone can do it in...

    Text Solution

    |

  16. A can do a piece of work in 10 days, B can do it in 12 days and C can ...

    Text Solution

    |

  17. A can do a piece of work in 5 days, B can do it in 10 days. With the h...

    Text Solution

    |

  18. A can do a piece of work in 8 days, B can do it in 16 days, while C ca...

    Text Solution

    |

  19. A can do a piece of work in 10 days, B can do it in 15 days working to...

    Text Solution

    |

  20. A can do a piece of work in 24 days, while B can do it in 30 days. Wit...

    Text Solution

    |