A can complete a work in 12 days, B in 15 days. Find the time taken by them: if A started two days later, in comparison to B.

Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A can complete a work in 12 days, B in 15 days. Find the time taken by them: if B started two days later, in comparison to A

A can complete a work in 12 days, B in 15 days. Find the time taken by them: if A leaves two days before the actual completion of the work.

A can complete a work in 12 days, B in 15 days. Find the time taken by them: if B leaves two days before the scheduled completion of the work.

A can complete a work in 15 days, B in 18 days. Find the time taken by them: if A leaves two days before the scheduled completion of the work.

A can complete a work in 12 days, B in 15 days. Find the time taken by them: when A and B worked alternatively started by B.

A can complete a work in 12 days, B in 15 days. Find the time taken by them: if B does negative work. with his same work rate.

A can complete a work in 12 days, B in 15 days. Find the time taken by them: when A and B worked together, when A and B worked alternatively and worked started by A

A can complete a work in 12 days and B complete the same work in 15 days. Find the time taken by them when A and B worked together.

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  2. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  3. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  4. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  5. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  6. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  7. A can complete a work in 15 days, B in 18 days. Find the time taken by...

    Text Solution

    |

  8. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  9. A can complete a work in 12 days, B in 15 days. Find the time taken by...

    Text Solution

    |

  10. A can complete a work in 16 days, B in 12 days and C in l5 days. All o...

    Text Solution

    |

  11. A alone con finish a piece of work in 12 days and B alone can do it in...

    Text Solution

    |

  12. A can do a piece of work in 10 days, B can do it in 12 days and C can ...

    Text Solution

    |

  13. A can do a piece of work in 5 days, B can do it in 10 days. With the h...

    Text Solution

    |

  14. A can do a piece of work in 8 days, B can do it in 16 days, while C ca...

    Text Solution

    |

  15. A can do a piece of work in 10 days, B can do it in 15 days working to...

    Text Solution

    |

  16. A can do a piece of work in 24 days, while B can do it in 30 days. Wit...

    Text Solution

    |

  17. A can do a piece of work in 10 days. B can do it in 24 days. If C also...

    Text Solution

    |

  18. A can do a piece of work in 14 days while B can do it in 28 days. In h...

    Text Solution

    |

  19. A can do a piece of work in 24 days. If B is 60% more efficient than A...

    Text Solution

    |

  20. A is twice as good a workman as B and together they finish a piece of ...

    Text Solution

    |