X is 4 times more efficient as Y, then t...

X is 4 times more efficient as Y, then the number of days taken by X and Y are in the ratio :

A

0.33402777777778

B

0.045138888888889

C

0.25555555555556

D

0.20902777777778

Text Solution

Verified by Experts

The correct Answer is:
B
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

X can do a piece of work in 25 days. Y is 25% more efficient than X. The number of days taken by Y is :

A is thrice efficient as B and C is twice as efficient as B. What is the ratio of number of days taken by A, B and C, when the work individually?

Ajit is 3 times as efficient as Bablu, then the ratio of number of days required by each to work alone, completely?

meenu is 3 times as efficient as mamta, then the ratio of number of days required by each to work alone, completely?

A is three times more efficient than B hence he takes 60 days less days taken by B in a certain task In how many days will both complete this work?

If X works 3 tims as fast as Y and is able to complete, a work in 40 days less than the number of days taken by Y, then find the time in which they cn complete the work working together.

X works 3 times as fast as Y and is able to complete a work in40 days less than the number of days taken by Y. Find the time in which they can complete the work together.

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. A is thrice efficient as B and C is twice as efficient as B. What is t...

    Text Solution

    |

  2. meenu is 3 times as efficient as mamta, then the ratio of number of da...

    Text Solution

    |

  3. X is 4 times more efficient as Y, then the number of days taken by X a...

    Text Solution

    |

  4. If A takes 4//5 days as B-takes and working together they require (20)...

    Text Solution

    |

  5. A is thrice as efficient as B. If B takes 8 days more than A, what is...

    Text Solution

    |

  6. P and Q can do a piece of work in 8 days, Q and R can do the same work...

    Text Solution

    |

  7. A and B can do a piece of work in 12 days, B and C in 15 days C and A ...

    Text Solution

    |

  8. Ganga, Jamuna and Saraswati can do a piece of work, working together, ...

    Text Solution

    |

  9. A can finish a work in 12 days and B can do it in 15 days. ’After A ha...

    Text Solution

    |

  10. Raja can do a piece of work in 14 days, while Rani can do the same wor...

    Text Solution

    |

  11. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  12. Sonu can do a piece of work in 20 days. He started the work and left a...

    Text Solution

    |

  13. Efficiency of Asha is 25% more than Usha and Usha takes 25 days to co...

    Text Solution

    |

  14. Krishna can do a work in 10 days while Mohan can do the same work in 2...

    Text Solution

    |

  15. Kareena can do a piece of work in 9 days and Karishma can do the same ...

    Text Solution

    |

  16. Kavita, Babita and Samita started a work. 5 days later Samita left the...

    Text Solution

    |

  17. The ratio of efficiency of A is to C is.5 :3 The ratio of number of d...

    Text Solution

    |

  18. Anand can do a piece of work in 45 days, but Bahuguna can do the same ...

    Text Solution

    |

  19. Chandni and Divakar can do a piece of work in 9 days and 12 days respe...

    Text Solution

    |

  20. Fatima and Zahira can do a piece of work in 12 days and 15 days respec...

    Text Solution

    |