If A takes 4//5 days as B-takes and work...

If A takes `4//5` days as B-takes and working together they require `(20)/3` days to complete the whole work. What is the efficiency of B ?

A

6`2/3%`

B

`16%`

C

`5.55%`

D

8`1/3%`

Text Solution

Verified by Experts

Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A and B together can complete a task in 12 days. However, if A works alone, completes half the job and leaves and then B works alone and completes the rest of the work, it takes 25 days in all to complete the work. If B is more efficient than A, how many days would it have taken B to do the work by herself?

To complete a certain work, C working alone takes twice as long as A and B working together. A working alone takes 3 times as long as B and C working together. All the three together can complete the work in 5 days. How long would each take to complete th work individually?

A complete (7)/(10) of a work in 15 days.After that he completes the work in 4 days with help from B.Find the number of days to complete the whole work if A and b work together from start.

A can do a piece of work in 10 days and B in 20 days.They begin together but A leaves 2 days before the completion of the work.The whole work will be done in?

A's 2 days' work is equal to B's 3days' work. a complete work in 8 days then to complete the work B will take

A and B on working together can complete a work in 4 days. A alone takes 6 days less than B alone takes. In how many days C alone can complete the work if he is 50% more efficient than B?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. meenu is 3 times as efficient as mamta, then the ratio of number of da...

    Text Solution

    |

  2. X is 4 times more efficient as Y, then the number of days taken by X a...

    Text Solution

    |

  3. If A takes 4//5 days as B-takes and working together they require (20)...

    Text Solution

    |

  4. A is thrice as efficient as B. If B takes 8 days more than A, what is...

    Text Solution

    |

  5. P and Q can do a piece of work in 8 days, Q and R can do the same work...

    Text Solution

    |

  6. A and B can do a piece of work in 12 days, B and C in 15 days C and A ...

    Text Solution

    |

  7. Ganga, Jamuna and Saraswati can do a piece of work, working together, ...

    Text Solution

    |

  8. A can finish a work in 12 days and B can do it in 15 days. ’After A ha...

    Text Solution

    |

  9. Raja can do a piece of work in 14 days, while Rani can do the same wor...

    Text Solution

    |

  10. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  11. Sonu can do a piece of work in 20 days. He started the work and left a...

    Text Solution

    |

  12. Efficiency of Asha is 25% more than Usha and Usha takes 25 days to co...

    Text Solution

    |

  13. Krishna can do a work in 10 days while Mohan can do the same work in 2...

    Text Solution

    |

  14. Kareena can do a piece of work in 9 days and Karishma can do the same ...

    Text Solution

    |

  15. Kavita, Babita and Samita started a work. 5 days later Samita left the...

    Text Solution

    |

  16. The ratio of efficiency of A is to C is.5 :3 The ratio of number of d...

    Text Solution

    |

  17. Anand can do a piece of work in 45 days, but Bahuguna can do the same ...

    Text Solution

    |

  18. Chandni and Divakar can do a piece of work in 9 days and 12 days respe...

    Text Solution

    |

  19. Fatima and Zahira can do a piece of work in 12 days and 15 days respec...

    Text Solution

    |

  20. The first term of an A.P. is 3 and its common difference is 4. The 11t...

    Text Solution

    |