Home
Class 14
MATHS
Ganga, Jamuna and Saraswati can do a pie...

Ganga, Jamuna and Saraswati can do a piece of work, working together, in 1 day. Ganga is thrice efficient as Jamuna and Jamuna takes twice the number of days as Saraswati takes to do it alone. What is the difference between the number of days taken by Ganga and Saraswati?

A

1

B

2

C

3

D

4

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's denote the efficiencies and the number of days taken by each person to complete the work. ### Step 1: Define Variables Let: - The efficiency of Jamuna = \( k \) (units of work per day) - The efficiency of Ganga = \( 3k \) (since Ganga is thrice as efficient as Jamuna) - The efficiency of Saraswati = \( x \) ### Step 2: Relate Jamuna and Saraswati According to the problem, Jamuna takes twice the number of days as Saraswati to complete the work. If we denote the number of days taken by Saraswati to complete the work alone as \( d \), then: - Jamuna takes \( 2d \) days to complete the work. The efficiency can be expressed as: - Efficiency of Jamuna = \( \frac{1}{2d} \) - Efficiency of Saraswati = \( \frac{1}{d} \) From the above, we know: \[ k = \frac{1}{2d} \quad \text{(1)} \] \[ x = \frac{1}{d} \quad \text{(2)} \] ### Step 3: Relate Efficiencies Since we know that Jamuna's efficiency \( k \) is also related to Saraswati's efficiency \( x \): \[ k = \frac{1}{2} x \quad \text{(from (2))} \] ### Step 4: Substitute and Solve Now, substituting \( k \) from (1) into the equation \( k = \frac{1}{2} x \): \[ \frac{1}{2d} = \frac{1}{2} \left(\frac{1}{d}\right) \] This confirms that both expressions for \( k \) and \( x \) are consistent. ### Step 5: Total Efficiency Now, the total efficiency when Ganga, Jamuna, and Saraswati work together is: \[ \text{Total Efficiency} = 3k + k + x = 3k + k + 2k = 6k \] Since they can complete the work in 1 day, the total efficiency is equal to 1 unit of work: \[ 6k = 1 \quad \Rightarrow \quad k = \frac{1}{6} \] ### Step 6: Find Individual Efficiencies Now substituting \( k \) back: - Efficiency of Jamuna = \( k = \frac{1}{6} \) - Efficiency of Ganga = \( 3k = \frac{3}{6} = \frac{1}{2} \) - Efficiency of Saraswati = \( x = 2k = \frac{2}{6} = \frac{1}{3} \) ### Step 7: Calculate Days Taken Now, we can find the number of days taken by each: - Days taken by Ganga = \( \frac{1}{\text{Efficiency of Ganga}} = \frac{1}{\frac{1}{2}} = 2 \) days - Days taken by Saraswati = \( \frac{1}{\text{Efficiency of Saraswati}} = \frac{1}{\frac{1}{3}} = 3 \) days ### Step 8: Find the Difference Finally, the difference between the number of days taken by Ganga and Saraswati is: \[ \text{Difference} = 3 - 2 = 1 \text{ day} \] ### Final Answer The difference between the number of days taken by Ganga and Saraswati is **1 day**. ---
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A is thrice as efficient as B. If B takes 8 days more than A, what is the number of days taken by A to finish the whole work, alone?

P can do a piece of work in 9 days.Q is 50% more efficient than P. The number of days it takes for Q to do the same piece of work is :

A is thrice as efficient as B.A and B cam complete a piece of work in 12 days. Find the number of days in which A alone complete it.

A can do a piece of work in 24 days. If B is 60% more efficient than A, then the number of days required by B to do the same piece of work is :

A is thrice as fast as B. If B can do a piece of work in 60 days, the number of days they take to complete the work is ……..

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. P and Q can do a piece of work in 8 days, Q and R can do the same work...

    Text Solution

    |

  2. A and B can do a piece of work in 12 days, B and C in 15 days C and A ...

    Text Solution

    |

  3. Ganga, Jamuna and Saraswati can do a piece of work, working together, ...

    Text Solution

    |

  4. A can finish a work in 12 days and B can do it in 15 days. ’After A ha...

    Text Solution

    |

  5. Raja can do a piece of work in 14 days, while Rani can do the same wor...

    Text Solution

    |

  6. A and B can complete a task in 30 days when working together after A a...

    Text Solution

    |

  7. Sonu can do a piece of work in 20 days. He started the work and left a...

    Text Solution

    |

  8. Efficiency of Asha is 25% more than Usha and Usha takes 25 days to co...

    Text Solution

    |

  9. Krishna can do a work in 10 days while Mohan can do the same work in 2...

    Text Solution

    |

  10. Kareena can do a piece of work in 9 days and Karishma can do the same ...

    Text Solution

    |

  11. Kavita, Babita and Samita started a work. 5 days later Samita left the...

    Text Solution

    |

  12. The ratio of efficiency of A is to C is.5 :3 The ratio of number of d...

    Text Solution

    |

  13. Anand can do a piece of work in 45 days, but Bahuguna can do the same ...

    Text Solution

    |

  14. Chandni and Divakar can do a piece of work in 9 days and 12 days respe...

    Text Solution

    |

  15. Fatima and Zahira can do a piece of work in 12 days and 15 days respec...

    Text Solution

    |

  16. The first term of an A.P. is 3 and its common difference is 4. The 11t...

    Text Solution

    |

  17. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  18. The number of days required by A, B and C to work individually is 6, 1...

    Text Solution

    |

  19. A takes 6 days less than B to do a certain job and 2 days more than C....

    Text Solution

    |

  20. A and B undertook a work for Rs. 350. A got Rs. 150 more than that of ...

    Text Solution

    |