15 persons can do a piece of work in 12 days. How many more people are required to complete the work in 10 days?

A

4

B

5

C

3

D

none of these

Text Solution

Verified by Experts

The correct Answer is:
C
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

30 persons can do a piece of work in 24 days. How many more people are required to complete the work in 20 days?

If 40 persons can do a piece of work in 14 days, then the number of persons required to complete the work in 28 days.

35 women can do a piece of work in 15 days. How many women would be required to do the same work in 25 days?

Twelve persons can do a piece of work in 20 days. How many persons are required to do the same in 24 days?

If 20 persons can do a piece of work in 7 days, then the number of persons required to complete the work in 28 days:

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. Colonel, Major and General started a work together fort ₹ 816. Colonel...

    Text Solution

    |

  2. Sharma is 20% less efficient than Kelkar. If Kelkar can do a piece of ...

    Text Solution

    |

  3. 15 persons can do a piece of work in 12 days. How many more people are...

    Text Solution

    |

  4. 12 women can do a piece of work in 20 days. If the 4 women deny to wor...

    Text Solution

    |

  5. 35 boys can do a piece of work in 15 days. The work will completed in ...

    Text Solution

    |

  6. 24 men can complete a job in 20 days. The number of men required to co...

    Text Solution

    |

  7. 16 men finished one-third work in 6 days. The number of additional men...

    Text Solution

    |

  8. If 10 persons can do a job in 20 days, then 20 person with twice the e...

    Text Solution

    |

  9. A certain-job was assigned to a group of men to do in 20 days. But 12 ...

    Text Solution

    |

  10. 30 workers can finish a work in 20 days. After how many days should 9 ...

    Text Solution

    |

  11. 25 men can complete a job in 30 days. After how many days should the s...

    Text Solution

    |

  12. A group of workers can complete a job in 120 days. If there were 4 mor...

    Text Solution

    |

  13. Mr. Modi can copy 40 pages in 10 minutes, Mr Xerox and Mr. Modi both w...

    Text Solution

    |

  14. 20 persons completed 1/3rd of the work in 12 days. How many more perso...

    Text Solution

    |

  15. A contractor undertook a work to complete in 60 days. But just after 2...

    Text Solution

    |

  16. 6 men or 10 women can reap a field in 15 days,then the number of days ...

    Text Solution

    |

  17. If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then ...

    Text Solution

    |

  18. 2 men or 5 women or 7 boys can finish a work in 469 days. then the num...

    Text Solution

    |

  19. 6 children and 2 men complete a certain piece of work in 6 days. Each ...

    Text Solution

    |

  20. 2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14...

    Text Solution

    |