35 boys can do a piece of work in 15 days. The work will completed in 25 days. How many boys did not turn up for the job?

A

14

B

20

C

6

D

7

Text Solution

Verified by Experts

The correct Answer is:
A
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

2 men and 7 boys can do a piece of work in 4 days.The same work is done in 3 days by 4 men and 4 boys.How long would it take one man and one boy to do it?

P can do a piece of work in 25 days and Q can do the same work in 15 days. In how many days they can complete the work by working together?

1 man or 2 boys or 3 girls can do a piece of work in 88 days. In how many days one man , one boy and one girl can do the same work ?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. 15 persons can do a piece of work in 12 days. How many more people are...

    Text Solution

    |

  2. 12 women can do a piece of work in 20 days. If the 4 women deny to wor...

    Text Solution

    |

  3. 35 boys can do a piece of work in 15 days. The work will completed in ...

    Text Solution

    |

  4. 24 men can complete a job in 20 days. The number of men required to co...

    Text Solution

    |

  5. 16 men finished one-third work in 6 days. The number of additional men...

    Text Solution

    |

  6. If 10 persons can do a job in 20 days, then 20 person with twice the e...

    Text Solution

    |

  7. A certain-job was assigned to a group of men to do in 20 days. But 12 ...

    Text Solution

    |

  8. 30 workers can finish a work in 20 days. After how many days should 9 ...

    Text Solution

    |

  9. 25 men can complete a job in 30 days. After how many days should the s...

    Text Solution

    |

  10. A group of workers can complete a job in 120 days. If there were 4 mor...

    Text Solution

    |

  11. Mr. Modi can copy 40 pages in 10 minutes, Mr Xerox and Mr. Modi both w...

    Text Solution

    |

  12. 20 persons completed 1/3rd of the work in 12 days. How many more perso...

    Text Solution

    |

  13. A contractor undertook a work to complete in 60 days. But just after 2...

    Text Solution

    |

  14. 6 men or 10 women can reap a field in 15 days,then the number of days ...

    Text Solution

    |

  15. If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then ...

    Text Solution

    |

  16. 2 men or 5 women or 7 boys can finish a work in 469 days. then the num...

    Text Solution

    |

  17. 6 children and 2 men complete a certain piece of work in 6 days. Each ...

    Text Solution

    |

  18. 2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14...

    Text Solution

    |

  19. A and C can finish a work in 40 days. They worked at it for 10 days an...

    Text Solution

    |

  20. The ratio of efficiencies of A , B & C is 14:9:7 . A, B and C received...

    Text Solution

    |