Home
Class 14
MATHS
30 workers can finish a work in 20 days....

30 workers can finish a work in 20 days. After how many days should 9 workers leave the job so that the work is completed in total 26 days if all the 30 workers started the work.

A

12

B

10

C

6

D

none of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will follow these steps: ### Step 1: Understand the Problem We know that 30 workers can complete a job in 20 days. We need to find out after how many days 9 workers should leave the job so that the total work is completed in 26 days. ### Step 2: Calculate Total Work First, we calculate the total amount of work in terms of worker-days. - Total work (W) = Number of workers × Number of days = 30 workers × 20 days = 600 worker-days. ### Step 3: Define Variables Let \( X \) be the number of days after which 9 workers leave the job. This means that for the first \( X \) days, all 30 workers are working. ### Step 4: Calculate Work Done in First X Days The work done by 30 workers in \( X \) days is: - Work done = Number of workers × Number of days = 30 workers × \( X \) days = \( 30X \) worker-days. ### Step 5: Calculate Remaining Work The total work is 600 worker-days. The remaining work after \( X \) days is: - Remaining work = Total work - Work done in first \( X \) days = \( 600 - 30X \). ### Step 6: Determine Remaining Days After \( X \) days, the total time to complete the work is 26 days. Therefore, the remaining days after \( X \) days is: - Remaining days = Total days - Days worked = \( 26 - X \). ### Step 7: Calculate Work Done by Remaining Workers After \( X \) days, 21 workers (30 - 9) will continue the work for \( 26 - X \) days. The work done by these 21 workers is: - Work done = Number of workers × Number of days = 21 workers × \( (26 - X) \) days = \( 21(26 - X) \) worker-days. ### Step 8: Set Up the Equation The total work done must equal the total work required: \[ 30X + 21(26 - X) = 600. \] ### Step 9: Solve the Equation Expanding the equation: \[ 30X + 546 - 21X = 600. \] Combine like terms: \[ 9X + 546 = 600. \] Subtract 546 from both sides: \[ 9X = 54. \] Divide by 9: \[ X = 6. \] ### Conclusion Thus, 9 workers should leave the job after 6 days.
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

30 persons can finish a job in20 days. After 6 days how many persons should leave the job, so that work is completedina total of 26 days?

30 girls can finish a work in 40 days. After how many days should 10 girls leave the work so that it may be finished in 46 days, if all the 30 girls started the work?

42 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

56 workers can reap a field in 8 days. If the work is to be completed in 7 days, the extra workers needed are:

25 men can complete a job in 30 days. After how many days should the strength of work force be increased by 50 men so that the work will be completed (2)/(3)rd in of the actual time:

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. If 10 persons can do a job in 20 days, then 20 person with twice the e...

    Text Solution

    |

  2. A certain-job was assigned to a group of men to do in 20 days. But 12 ...

    Text Solution

    |

  3. 30 workers can finish a work in 20 days. After how many days should 9 ...

    Text Solution

    |

  4. 25 men can complete a job in 30 days. After how many days should the s...

    Text Solution

    |

  5. A group of workers can complete a job in 120 days. If there were 4 mor...

    Text Solution

    |

  6. Mr. Modi can copy 40 pages in 10 minutes, Mr Xerox and Mr. Modi both w...

    Text Solution

    |

  7. 20 persons completed 1/3rd of the work in 12 days. How many more perso...

    Text Solution

    |

  8. A contractor undertook a work to complete in 60 days. But just after 2...

    Text Solution

    |

  9. 6 men or 10 women can reap a field in 15 days,then the number of days ...

    Text Solution

    |

  10. If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then ...

    Text Solution

    |

  11. 2 men or 5 women or 7 boys can finish a work in 469 days. then the num...

    Text Solution

    |

  12. 6 children and 2 men complete a certain piece of work in 6 days. Each ...

    Text Solution

    |

  13. 2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14...

    Text Solution

    |

  14. A and C can finish a work in 40 days. They worked at it for 10 days an...

    Text Solution

    |

  15. The ratio of efficiencies of A , B & C is 14:9:7 . A, B and C received...

    Text Solution

    |

  16. 314 weavers weaves 6594 shawls in 1//6 hours what is the number of sha...

    Text Solution

    |

  17. Three men and two women can do a piece of work in 4 days, while two me...

    Text Solution

    |

  18. 30 girls can finish a work in 40 days. After how many days should 10 g...

    Text Solution

    |

  19. If 8 women collect 200 kg of tea leaves in 10 hours. How many more (in...

    Text Solution

    |

  20. 450 man-days of work can be completed by a certain number of men in so...

    Text Solution

    |