Home
Class 14
MATHS
A group of workers can complete a job in...

A group of workers can complete a job in 120 days. If there were 4 more such workers then the work could be finished in 12 days less what was the actual strength of workers?

A

30 workers

B

40 workers

C

42 workers

D

36 workers

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will use the concept of work done by a group of workers over a period of time. ### Step 1: Define the variables Let the actual strength of the workers be \( x \). This means there are \( x \) workers. ### Step 2: Determine the total work done The group of workers can complete the job in 120 days. Therefore, the total work \( W \) can be expressed as: \[ W = \text{Number of workers} \times \text{Number of days} = x \times 120 \] ### Step 3: Analyze the scenario with additional workers If there were 4 more workers, the number of workers would be \( x + 4 \). The work could then be finished in 12 days less, which means it would take \( 120 - 12 = 108 \) days. ### Step 4: Express the total work with the additional workers The total work done with the additional workers can also be expressed as: \[ W = (x + 4) \times 108 \] ### Step 5: Set the two expressions for work equal to each other Since the total work \( W \) is the same in both scenarios, we can set the equations equal to each other: \[ x \times 120 = (x + 4) \times 108 \] ### Step 6: Expand and simplify the equation Expanding the right side: \[ 120x = 108x + 432 \] ### Step 7: Rearrange the equation to isolate \( x \) Subtract \( 108x \) from both sides: \[ 120x - 108x = 432 \] \[ 12x = 432 \] ### Step 8: Solve for \( x \) Now, divide both sides by 12: \[ x = \frac{432}{12} = 36 \] ### Conclusion The actual strength of the workers is \( x = 36 \).
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A certain number of persons can complete a piece of work in 55 days. If there were 6 persons more, the work could be finished in 11 days less. How many persons were originally there?

A certain number of men can do a work in 60 days. If there were 8 men more it could be finished in 10 days less. How many men are there?

A certain number of men can do a work in 35 days. If there were 10 men more it could be finished in 10 days less. How many men are there?

'x' number of men can finish a piece of work in 30 days. If there were 6 men more, the work could be finished in 10 days less. The original number of men is

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. 30 workers can finish a work in 20 days. After how many days should 9 ...

    Text Solution

    |

  2. 25 men can complete a job in 30 days. After how many days should the s...

    Text Solution

    |

  3. A group of workers can complete a job in 120 days. If there were 4 mor...

    Text Solution

    |

  4. Mr. Modi can copy 40 pages in 10 minutes, Mr Xerox and Mr. Modi both w...

    Text Solution

    |

  5. 20 persons completed 1/3rd of the work in 12 days. How many more perso...

    Text Solution

    |

  6. A contractor undertook a work to complete in 60 days. But just after 2...

    Text Solution

    |

  7. 6 men or 10 women can reap a field in 15 days,then the number of days ...

    Text Solution

    |

  8. If 2 men or 3 women or 4 boys can do a piece of work in 52 days, then ...

    Text Solution

    |

  9. 2 men or 5 women or 7 boys can finish a work in 469 days. then the num...

    Text Solution

    |

  10. 6 children and 2 men complete a certain piece of work in 6 days. Each ...

    Text Solution

    |

  11. 2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14...

    Text Solution

    |

  12. A and C can finish a work in 40 days. They worked at it for 10 days an...

    Text Solution

    |

  13. The ratio of efficiencies of A , B & C is 14:9:7 . A, B and C received...

    Text Solution

    |

  14. 314 weavers weaves 6594 shawls in 1//6 hours what is the number of sha...

    Text Solution

    |

  15. Three men and two women can do a piece of work in 4 days, while two me...

    Text Solution

    |

  16. 30 girls can finish a work in 40 days. After how many days should 10 g...

    Text Solution

    |

  17. If 8 women collect 200 kg of tea leaves in 10 hours. How many more (in...

    Text Solution

    |

  18. 450 man-days of work can be completed by a certain number of men in so...

    Text Solution

    |

  19. 4 boys and 5 girls can do a piece of work in 10 days. 6 boys and 6 gir...

    Text Solution

    |

  20. If 20 engineers and 20 workers can together construct a 20 km road in ...

    Text Solution

    |