The ratio of efficiencies of A , B & C is 14:9:7 . A, B and C received total ₹ 27,000 for the whole work. as What is the share of C, if the. money is distributed. in the ratio of amount of work done, individually?

A

2700

B

7200

C

14400

D

6300

Text Solution

AI Generated Solution

The correct Answer is:
To find the share of C when the total amount of ₹ 27,000 is distributed according to the efficiencies of A, B, and C, we can follow these steps: ### Step 1: Understand the ratio of efficiencies The efficiencies of A, B, and C are given as 14:9:7. This means that for every 30 parts of work done, A does 14 parts, B does 9 parts, and C does 7 parts. ### Step 2: Calculate the total parts of work To find the total parts of work, we add the parts of A, B, and C: \[ \text{Total parts} = 14 + 9 + 7 = 30 \] ### Step 3: Determine the share of C C's share in the total work is represented by the 7 parts out of the total 30 parts. Therefore, C's share of the total payment can be calculated as: \[ \text{C's share} = \frac{\text{C's parts}}{\text{Total parts}} \times \text{Total payment} \] Substituting the values: \[ \text{C's share} = \frac{7}{30} \times 27000 \] ### Step 4: Calculate C's share Now, we perform the calculation: \[ \text{C's share} = \frac{7 \times 27000}{30} \] Calculating \( \frac{27000}{30} \): \[ \frac{27000}{30} = 900 \] Now multiplying by 7: \[ \text{C's share} = 7 \times 900 = 6300 \] ### Conclusion Thus, the share of C is ₹ 6,300. ---
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

The ratio of efficiencies of A,B and C is 6:5:4 and if A, B and C received total Rs. 27,000 for the whole work. What is the share of C, if the money is distributed in the ratio of amount of work done, individually?

If A is thrice as good as B in work then ratio of work done by A and B.

The ratio of working efficiency of A and B is 5:3 and the ratio of efficiency of B and C is 5:8. Who is the most efficient?

A, B and C can do a piece of work in 12 , 15 and 30 days respectively. If they do a work together, find the ratio in which the amount is to be distributed

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. 2 men and 3 women finish 25% of the work in 4 days, while 6 men and 14...

    Text Solution

    |

  2. A and C can finish a work in 40 days. They worked at it for 10 days an...

    Text Solution

    |

  3. The ratio of efficiencies of A , B & C is 14:9:7 . A, B and C received...

    Text Solution

    |

  4. 314 weavers weaves 6594 shawls in 1//6 hours what is the number of sha...

    Text Solution

    |

  5. Three men and two women can do a piece of work in 4 days, while two me...

    Text Solution

    |

  6. 30 girls can finish a work in 40 days. After how many days should 10 g...

    Text Solution

    |

  7. If 8 women collect 200 kg of tea leaves in 10 hours. How many more (in...

    Text Solution

    |

  8. 450 man-days of work can be completed by a certain number of men in so...

    Text Solution

    |

  9. 4 boys and 5 girls can do a piece of work in 10 days. 6 boys and 6 gir...

    Text Solution

    |

  10. If 20 engineers and 20 workers can together construct a 20 km road in ...

    Text Solution

    |

  11. (x-2) men can do a piece of work in x days and (x+7) men can do 75% of...

    Text Solution

    |

  12. A man, a woman and a girl worked for a contractor for the same 'period...

    Text Solution

    |

  13. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  14. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  15. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  16. Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and...

    Text Solution

    |

  17. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  18. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  19. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  20. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |