Home
Class 14
MATHS
450 man-days of work can be completed by...

450 man-days of work can be completed by a certain number of men in some days. If the number of people (men) are increased by 27, then the. number of day required to complete the same work is decreased- by 15. The number of days are required to complete the" three times work (than the previous/actual work) by 27 men?

A

50

B

60

C

54

D

45

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we will first define the variables and then set up the equations based on the information given in the question. ### Step 1: Define Variables Let: - \( N \) = initial number of men - \( D \) = initial number of days required to complete the work ### Step 2: Set Up the Equation for Work The total work can be expressed in terms of man-days: \[ \text{Total Work} = N \times D = 450 \text{ man-days} \] From this, we can express \( D \) in terms of \( N \): \[ D = \frac{450}{N} \] ### Step 3: Set Up the New Scenario When the number of men is increased by 27, the new number of men is \( N + 27 \) and the new number of days required is \( D - 15 \). The total work remains the same: \[ (N + 27)(D - 15) = 450 \] ### Step 4: Substitute \( D \) in the New Equation Substituting \( D = \frac{450}{N} \) into the new equation: \[ (N + 27)\left(\frac{450}{N} - 15\right) = 450 \] ### Step 5: Simplify the Equation Expanding the equation: \[ (N + 27)\left(\frac{450 - 15N}{N}\right) = 450 \] Multiplying both sides by \( N \): \[ (N + 27)(450 - 15N) = 450N \] Expanding this gives: \[ 450N + 12150 - 15N^2 - 405N = 450N \] This simplifies to: \[ 12150 - 15N^2 - 405N = 0 \] ### Step 6: Rearranging the Equation Rearranging gives us: \[ 15N^2 + 405N - 12150 = 0 \] Dividing the entire equation by 15: \[ N^2 + 27N - 810 = 0 \] ### Step 7: Solve the Quadratic Equation Using the quadratic formula \( N = \frac{-b \pm \sqrt{b^2 - 4ac}}{2a} \): Here, \( a = 1, b = 27, c = -810 \): \[ N = \frac{-27 \pm \sqrt{27^2 - 4 \times 1 \times (-810)}}{2 \times 1} \] Calculating the discriminant: \[ 27^2 + 3240 = 729 + 3240 = 3969 \] Taking the square root: \[ \sqrt{3969} = 63 \] Now substituting back: \[ N = \frac{-27 \pm 63}{2} \] Calculating the two possible values for \( N \): 1. \( N = \frac{36}{2} = 18 \) 2. \( N = \frac{-90}{2} = -45 \) (not valid since number of men cannot be negative) Thus, \( N = 18 \). ### Step 8: Find Initial Days \( D \) Now substituting \( N \) back to find \( D \): \[ D = \frac{450}{N} = \frac{450}{18} = 25 \text{ days} \] ### Step 9: Calculate Days for Three Times the Work The total work for three times the original work is: \[ 3 \times 450 = 1350 \text{ man-days} \] Now, we need to find the number of days required by 27 men to complete this work: \[ \text{Days} = \frac{1350}{27} = 50 \text{ days} \] ### Final Answer The number of days required to complete three times the work by 27 men is **50 days**. ---
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

If 12 men can finish a work in 20 days , then find the number of days required to complete the same work by15 men .

If 5 men do a piece of work in 28 days, then the number of persons required to do the same work in 7 days is

Twelve men are required to complete a work in 24 days.How many men are required to complete twice the work in 16 days?

10 men can make a wall in 8 days. How many men required to complete the same work in half day

Had been one men less, then the number of days required to do a piece of work would have been one more. If the number of Man Days required to complete the work is 56, how many workers were there?

24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. 30 girls can finish a work in 40 days. After how many days should 10 g...

    Text Solution

    |

  2. If 8 women collect 200 kg of tea leaves in 10 hours. How many more (in...

    Text Solution

    |

  3. 450 man-days of work can be completed by a certain number of men in so...

    Text Solution

    |

  4. 4 boys and 5 girls can do a piece of work in 10 days. 6 boys and 6 gir...

    Text Solution

    |

  5. If 20 engineers and 20 workers can together construct a 20 km road in ...

    Text Solution

    |

  6. (x-2) men can do a piece of work in x days and (x+7) men can do 75% of...

    Text Solution

    |

  7. A man, a woman and a girl worked for a contractor for the same 'period...

    Text Solution

    |

  8. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  9. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  10. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  11. Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and...

    Text Solution

    |

  12. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  13. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  14. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  15. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  16. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  17. A, B and C are three book binders. A takes 8 .minutes, B takes 12 minu...

    Text Solution

    |

  18. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  19. B and C are equally efficient, but the efficiency of-A is half of each...

    Text Solution

    |

  20. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |