Home
Class 14
MATHS
(x-2) men can do a piece of work in x da...

`(x-2)` men can do a piece of work in x days and `(x+7)` men can do `75%` of the same work in `(x-10)` days. Then in how many days can `(x+10)` men finish the work?

A

27 days

B

12 days

C

25 days

D

18 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, let's break it down: ### Step 1: Understand the Work Done Let the total work be denoted as \( W \). From the problem, we know: - \( (x-2) \) men can complete the work in \( x \) days. - Therefore, the work done by \( (x-2) \) men in \( x \) days is: \[ W = (x-2) \times x \] ### Step 2: Work Done by \( (x+7) \) Men Next, we know that \( (x+7) \) men can complete \( 75\% \) of the work in \( (x-10) \) days. Thus: \[ 0.75W = (x+7) \times (x-10) \] ### Step 3: Substitute \( W \) in the Second Equation Substituting \( W \) from Step 1 into the second equation: \[ 0.75 \times (x-2) \times x = (x+7) \times (x-10) \] ### Step 4: Expand Both Sides Expanding both sides: - Left side: \[ 0.75(x^2 - 2x) = 0.75x^2 - 1.5x \] - Right side: \[ (x+7)(x-10) = x^2 - 10x + 7x - 70 = x^2 - 3x - 70 \] ### Step 5: Set the Equation Setting the two sides equal: \[ 0.75x^2 - 1.5x = x^2 - 3x - 70 \] ### Step 6: Rearrange the Equation Rearranging gives: \[ 0.75x^2 - x^2 + 3x - 1.5x + 70 = 0 \] \[ -0.25x^2 + 1.5x + 70 = 0 \] Multiplying through by -4 to eliminate the decimal: \[ x^2 - 6x - 280 = 0 \] ### Step 7: Factor the Quadratic Equation Now we need to factor the quadratic equation: \[ x^2 - 6x - 280 = 0 \] To factor, we look for two numbers that multiply to -280 and add to -6. The numbers are -20 and 14: \[ (x - 20)(x + 14) = 0 \] Thus, \( x = 20 \) or \( x = -14 \). Since \( x \) must be positive, we take \( x = 20 \). ### Step 8: Calculate the Number of Days for \( (x+10) \) Men Now substituting \( x = 20 \): - The number of men becomes: \[ x + 10 = 20 + 10 = 30 \text{ men} \] - The total work \( W \) is: \[ W = (20 - 2) \times 20 = 18 \times 20 = 360 \] - The number of days \( D \) for \( 30 \) men to finish the work is: \[ D = \frac{W}{\text{Number of Men}} = \frac{360}{30} = 12 \text{ days} \] ### Final Answer Thus, \( (x+10) \) men can finish the work in **12 days**. ---
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

2 men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days. In how many days can 2 men and 1 boy do the same work ?

3 men can do a piece of worki n 18 days , 6 boys can also do the same work in 18 days. In how many days, 4 men and 4 boys together will finish the work?

2men and 3 boys can do a piece of work in 10 days while 3 men and 2 boys can do the same work in 8 days.In how many days can 2 men and 1 boy do the work?

7 men can complete a work in 52 days. In how many days will 13 men finish the same work.

If 4 men or 7 women can do a work in 60 days, then in how many days will 8 men and 7 women finish the same work?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. 4 boys and 5 girls can do a piece of work in 10 days. 6 boys and 6 gir...

    Text Solution

    |

  2. If 20 engineers and 20 workers can together construct a 20 km road in ...

    Text Solution

    |

  3. (x-2) men can do a piece of work in x days and (x+7) men can do 75% of...

    Text Solution

    |

  4. A man, a woman and a girl worked for a contractor for the same 'period...

    Text Solution

    |

  5. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  6. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  7. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  8. Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and...

    Text Solution

    |

  9. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  10. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  11. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  12. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  13. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  14. A, B and C are three book binders. A takes 8 .minutes, B takes 12 minu...

    Text Solution

    |

  15. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  16. B and C are equally efficient, but the efficiency of-A is half of each...

    Text Solution

    |

  17. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  18. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  19. A is twice efficient as B and together they do the same work, in as mu...

    Text Solution

    |

  20. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |