Home
Class 14
MATHS
33 men can do a job in 30 days. If 44 me...

33 men can do a job in 30 days. If 44 men started the job together and after every day of the work, one person leaves. What is the minimum number of days required to complete the whole work?

A

21

B

42

C

45

D

none of these

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem step by step, we need to determine how many days it will take for 44 men to complete a job if one man leaves at the end of each day. ### Step 1: Calculate the total work We know that 33 men can complete the work in 30 days. Therefore, the total work can be calculated as follows: \[ \text{Total Work} = \text{Number of Men} \times \text{Number of Days} = 33 \times 30 = 990 \text{ man-days} \] ### Step 2: Determine the daily work done by 44 men On the first day, 44 men will work together. Thus, the work done on the first day is: \[ \text{Work done on Day 1} = 44 \text{ units} \] ### Step 3: Calculate the work done on subsequent days Since one man leaves at the end of each day, the number of men working each day decreases by 1. Therefore, the work done on each subsequent day will be as follows: - Day 1: 44 men → 44 units - Day 2: 43 men → 43 units - Day 3: 42 men → 42 units - ... - Day N: \( (44 - (N - 1)) \) men → \( (44 - (N - 1)) \) units ### Step 4: Set up the equation for total work The total work done over N days can be expressed as the sum of an arithmetic series: \[ \text{Total Work} = 44 + 43 + 42 + \ldots + (44 - (N - 1)) \] This can be simplified using the formula for the sum of an arithmetic series: \[ \text{Sum} = \frac{N}{2} \times (\text{First Term} + \text{Last Term}) \] Where: - First Term = 44 - Last Term = \( 44 - (N - 1) = 45 - N \) Thus, the equation becomes: \[ \text{Total Work} = \frac{N}{2} \times (44 + (45 - N)) = \frac{N}{2} \times (89 - N) \] ### Step 5: Set the equation equal to total work and solve for N We know the total work is 990 units: \[ \frac{N}{2} \times (89 - N) = 990 \] Multiplying both sides by 2 to eliminate the fraction: \[ N(89 - N) = 1980 \] Rearranging gives us a quadratic equation: \[ N^2 - 89N + 1980 = 0 \] ### Step 6: Solve the quadratic equation Using the quadratic formula \( N = \frac{-b \pm \sqrt{b^2 - 4ac}}{2a} \): Here, \( a = 1, b = -89, c = 1980 \): \[ N = \frac{89 \pm \sqrt{(-89)^2 - 4 \times 1 \times 1980}}{2 \times 1} \] Calculating the discriminant: \[ (-89)^2 = 7921 \] \[ 4 \times 1 \times 1980 = 7920 \] \[ \sqrt{7921 - 7920} = \sqrt{1} = 1 \] Thus, substituting back into the formula: \[ N = \frac{89 \pm 1}{2} \] Calculating the two possible values for N: 1. \( N = \frac{90}{2} = 45 \) 2. \( N = \frac{88}{2} = 44 \) Since we need the minimum number of days, we take \( N = 45 \). ### Conclusion The minimum number of days required to complete the whole work is **45 days**.
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

If 30 men can do a job in 30 days, find what part of the job can be completed by 1 man in 1 day.

If 5 men can do a piece of work in 10 days and 12 women can do the same work in 15 days, the number of days required to complete the work by 5 men and 6 women is

A and B can do a job in 6 and 12 days respectively. They began the work together but A leaves after 3 days. Then, the total number of days needed for the completion of the work is

24 men can complete a job in 40 days. The number men required to complete the job in 32 days is :

24 men can complete a job in 20 days. The number of men required to complete the job in 16 days is :

A and B can complete a job in 24 days working together. A alone can complete it in 32 days. Both of them worked together for 8 days and then A left. The number of days B will take to complete the remaining job is

12 men finished frac(1)(4)th part of whole work in 6 days. Find the number of additional men required to complete the job innext 6 days.

6 men or 8 women can do a job in 10 days In how many days can 5 men and 9 women do the same job?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. (x-2) men can do a piece of work in x days and (x+7) men can do 75% of...

    Text Solution

    |

  2. A man, a woman and a girl worked for a contractor for the same 'period...

    Text Solution

    |

  3. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  4. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  5. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  6. Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and...

    Text Solution

    |

  7. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  8. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  9. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  10. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  11. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  12. A, B and C are three book binders. A takes 8 .minutes, B takes 12 minu...

    Text Solution

    |

  13. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  14. B and C are equally efficient, but the efficiency of-A is half of each...

    Text Solution

    |

  15. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  16. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  17. A is twice efficient as B and together they do the same work, in as mu...

    Text Solution

    |

  18. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  19. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  20. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |