Abhishek can do a piece of work in 40 da...

Abhishek can do a piece of work in 40 days. He alone worked at it for 8 days and then Bacchhan completed alone the rest work in 24 days. In how many days they will complete the whole work, working together?

A

`17 1/7` days

B

`18 1/7` days

C

`9 1/6` days

D

14 days

Text Solution

AI Generated Solution

The correct Answer is:
To solve the problem, we will follow these steps: ### Step 1: Determine Abhishek's Work Rate Abhishek can complete the work in 40 days. Therefore, his work rate per day is: \[ \text{Work Rate of Abhishek} = \frac{1}{40} \text{ (work per day)} \] ### Step 2: Calculate the Work Done by Abhishek in 8 Days In 8 days, the amount of work done by Abhishek is: \[ \text{Work Done by Abhishek} = 8 \times \frac{1}{40} = \frac{8}{40} = \frac{1}{5} \] ### Step 3: Determine the Remaining Work The total work can be considered as 1 unit. After Abhishek's contribution, the remaining work is: \[ \text{Remaining Work} = 1 - \frac{1}{5} = \frac{4}{5} \] ### Step 4: Calculate Bacchhan's Work Rate Bacchhan completed the remaining work in 24 days. Therefore, his work rate per day is: \[ \text{Work Rate of Bacchhan} = \frac{4/5}{24} = \frac{4}{120} = \frac{1}{30} \text{ (work per day)} \] ### Step 5: Calculate Combined Work Rate of Abhishek and Bacchhan Now, we can find their combined work rate: \[ \text{Combined Work Rate} = \text{Work Rate of Abhishek} + \text{Work Rate of Bacchhan} = \frac{1}{40} + \frac{1}{30} \] To add these fractions, we need a common denominator. The least common multiple of 40 and 30 is 120. \[ \frac{1}{40} = \frac{3}{120}, \quad \frac{1}{30} = \frac{4}{120} \] Thus, \[ \text{Combined Work Rate} = \frac{3}{120} + \frac{4}{120} = \frac{7}{120} \] ### Step 6: Calculate the Time Taken to Complete the Whole Work Together The time taken to complete the whole work together is the reciprocal of their combined work rate: \[ \text{Time} = \frac{1}{\text{Combined Work Rate}} = \frac{1}{\frac{7}{120}} = \frac{120}{7} \approx 17.14 \text{ days} \] ### Conclusion Abhishek and Bacchhan, working together, will complete the whole work in approximately 17.14 days. ---
Promotional Banner

Topper's Solved these Questions

  • THEORY OF EQUATIONS

    QUANTUM CAT|Exercise QUESTION BANK|573 Videos
  • TIME, SPEED AND DISTANCE

    QUANTUM CAT|Exercise QUESTION BANK|368 Videos

Similar Questions

Explore conceptually related problems

A can do a piece of work in 34 days. He worked for 14 days and then left. B completed the remaining work in 30 days. In how many days can B alone complete the work?

A can do a piece of work in 8 days, B can do it in 16 days, while C can do it in 80 days. In how many days they can complete the whole work, working together?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

A is twice as fast as B and together they can complete a work in 20 days. In how many days can A alone complete the work?

Vaibhav can do a piece of work in 60 days. He works there for 15 days and then Sandeep alone finishes the remaining work in 30 days. In how many days will Vaibhav and Sandeep working together finish the work?

If Rohit alone can complete one-fourth of a work in 32 days, then in how many days Rohit alone can complete the whole work?

QUANTUM CAT-TIME AND WORK-QUESTION BANK
  1. A man, a woman and a girl worked for a contractor for the same 'period...

    Text Solution

    |

  2. 33 men can do a job in 30 days. If 44 men started the job together and...

    Text Solution

    |

  3. Abhishek can do a piece of work in 40 days. He alone worked at it for ...

    Text Solution

    |

  4. C is twice efficient as A. B takes thrice as many days as C. A takes 1...

    Text Solution

    |

  5. Ahluwalia and Bimal together take 6 days to finish the work.'Bimal and...

    Text Solution

    |

  6. B is twice efficient as A and A can do a piece of work in 15 days. A s...

    Text Solution

    |

  7. A, B and C can complete a piece of-work in 15, 30 and 40 days respecti...

    Text Solution

    |

  8. There was a leakage in the container of the refined oil. If 11 kg oil ...

    Text Solution

    |

  9. A contractor undertook to complete the work in 40 days and he deployed...

    Text Solution

    |

  10. 7 Indian and 4 Chinese finish a job in 5 days. 7 Japanese and 3 Chines...

    Text Solution

    |

  11. A, B and C are three book binders. A takes 8 .minutes, B takes 12 minu...

    Text Solution

    |

  12. A piece of work can be completed by 10 men and 6 women in 18 days. Men...

    Text Solution

    |

  13. B and C are equally efficient, but the efficiency of-A is half of each...

    Text Solution

    |

  14. A can do a piece of work in 10 days, B in 15 days. They work together ...

    Text Solution

    |

  15. A can do a piece of work in 2 hours, B can do thrice the work in 8 hou...

    Text Solution

    |

  16. A is twice efficient as B and together they do the same work, in as mu...

    Text Solution

    |

  17. 4 men and 2 boys can finish a piece of work in 5 days. 3 women and 4 b...

    Text Solution

    |

  18. If m men can do a work in r days, then the number of days taken by (m+...

    Text Solution

    |

  19. Pipe A can fill a tank in 36 minutes and pipe B can fill it in 45 minu...

    Text Solution

    |

  20. Tap A can fill the empty tank in 12 hours, but due to a leak in the bo...

    Text Solution

    |